3827 W 58TH PL 90043

Certificate Information: 3827 W 58TH PL 90043

Application / Permit
20014-10000-05384
Plan Check / Job No.
B20LA22461
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED BATHROOM EXTENSION AND LAUNDRY ROOM ADDITION AT REAR OF (E) SFD.
Permit Issued
Issued on 4/16/2021
Issuing Office
Metro
Current Status
CofO Issued on 10/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2020 APPLICANT
Assigned to Plan Check Engineer 12/16/2020 LAWRENCE QUIRANTE
Corrections Issued 12/16/2020 LAWRENCE QUIRANTE
Plan Check Approved 2/18/2021 RICARDO RAMIREZ
Issued 4/16/2021 APPLICANT
Building Plans Picked Up 6/3/2021 APPLICANT
CofO in Progress 10/2/2023 ENRIQUE MIRELES
CofO in Progress 10/2/2023 ENRIQUE MIRELES
CofO Issued 10/9/2023 DEROLD HAUFF
Permit Finaled 10/9/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/22/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 1/22/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/22/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 12/22/2022 No Access for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 12/23/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/20/2023 Approved ENRIQUE MIRELES
Wood Frame 1/20/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/16/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 2/16/2023 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 2/16/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 2/16/2023 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 3/8/2023 Approved ENRIQUE MIRELES
Insulation 3/31/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/17/2023 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 4/17/2023 Approved ENRIQUE MIRELES
Final 7/21/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 7/21/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 7/21/2023 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 7/21/2023 Corrections Issued ENRIQUE MIRELES
Final 8/4/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 8/4/2023 Approved ENRIQUE MIRELES
Green Building Final 8/4/2023 Approved ENRIQUE MIRELES
Smoke Detectors 8/4/2023 Approved ENRIQUE MIRELES
Final 9/6/2023 Corrections Issued ENRIQUE MIRELES
Final 9/29/2023 OK to Issue CofO ENRIQUE MIRELES