949 S BRONSON AVE 90019
Certificate Information: 949 S BRONSON AVE 90019
- Application / Permit
- 20014-10000-05373
- Plan Check / Job No.
- B20LA22403
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION AND ADDITION OF GARAGE TO (N) A.D.U.PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/23/2021
- Issuing Office
- Current Status
- CofO Issued on 1/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2020 | LAWRENCE QUIRANTE |
| Corrections Issued | 12/23/2020 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 8/25/2021 | RAHEL BEYENE |
| Plan Check Approved | 11/3/2021 | RAHEL BEYENE |
| Issued | 11/23/2021 | APPLICANT |
| Building Plans Picked Up | 12/3/2021 | APPLICANT |
| CofO in Progress | 8/17/2022 | JEFFREY MEAD |
| CofO in Progress | 9/6/2022 | JULIAN AMAYA |
| CofO in Progress | 9/7/2022 | JEFFREY MEAD |
| Permit Finaled | 1/5/2023 | DEROLD HAUFF |
| CofO Issued | 1/5/2023 | DEROLD HAUFF |
| Permit Finaled | 1/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/22/2021 | RENZ SORIANO |
| HPOZ | Cleared | 3/17/2021 | AMANDA KAINER |
| Low Impact Development | Cleared | 6/18/2021 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 9/22/2021 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 9/22/2021 | RENZ SORIANO |
Contact Information
| Architect | Baek,, Sunpil; Lic. No.: C35323 | 3923 W 6TH ST SUITE 410 LOS ANGELES, CA 90020 |
| Contractor | Namu Development Inc; Lic. No.: 997839-B | 2333 BEVERLY BLVD #202-A LOS ANGELES, CA 90057 |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 815 FAIRVIEW AVE #205 SOUTH PASADENA, CA 91030 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/10/2021 | Approved | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 1/13/2022 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/14/2022 | Corrections Issued | JOSEPH MCGARRY |
| METHANE-Barrier | 1/14/2022 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 1/14/2022 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/21/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 2/1/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Underground Mechanical | 2/7/2022 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 2/16/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Rough | 2/16/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 2/16/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 2/16/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Pre-Inspection | 2/18/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Insulation | 2/23/2022 | Conditional Approval | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2022 | Not Ready for Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 3/23/2022 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2022 | Approved | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 4/5/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 4/5/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Green Building Rough | 4/5/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| HVAC-Rough | 4/5/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 4/5/2022 | Partial Approval | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 4/14/2022 | Corrections Issued | ADAM ESCOTO |
| HVAC-Final | 4/14/2022 | Corrections Issued | ADAM ESCOTO |
| HVAC-Rough | 4/14/2022 | Approved | ADAM ESCOTO |
| PLUMBING-Rough | 4/14/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 4/28/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Insulation | 5/9/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Insulation | 5/12/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Insulation | 5/17/2022 | Conditional Approval | ADAM ESCOTO |
| Insulation | 5/17/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 5/23/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 5/26/2022 | Approved | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 6/13/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Shower Pan | 6/13/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/17/2022 | Partial Approval | ADAM ESCOTO |
| Service/Power Release | 7/5/2022 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Final | 7/12/2022 | Partial Approval | JEFFREY MEAD |
| HVAC-Final | 7/12/2022 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Final | 7/12/2022 | Approved | JEFFREY MEAD |
| Service/Power Release | 7/12/2022 | Order to Comply Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/16/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 8/16/2022 | Approved | JEFFREY MEAD |
| Final | 8/16/2022 | Partial Inspection | JEFFREY MEAD |
| Green Building Final | 8/16/2022 | Approved | JEFFREY MEAD |
| Green Building Rough | 8/16/2022 | Approved | JEFFREY MEAD |
| HVAC-Final | 8/16/2022 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 8/16/2022 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 8/16/2022 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 8/16/2022 | Approved | JEFFREY MEAD |
| Smoke Detectors | 8/16/2022 | Approved | JEFFREY MEAD |
| Final | 9/6/2022 | OK to Issue CofO | JEFFREY MEAD |
| Service/Power Release | 9/6/2022 | Approved | JEFFREY MEAD |