11139 N CHIMINEAS AVE 91326
Certificate Information: 11139 N CHIMINEAS AVE 91326
- Application / Permit
- 20014-10000-05371
- Plan Check / Job No.
- B20LA22393
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMOLISH 2 EXISTING PATIO STRUCTURES. and GROUND FLOOR ADDITION TO EXISTING SFD WITH ATTACHED GARAGE AND NEW ATTACHED COVERED PATIO
- Permit Issued
- Issued on 4/16/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | TARIK SAOUD |
| Corrections Issued | 12/14/2020 | TARIK SAOUD |
| Quality Review Completed | 12/23/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/1/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 2/2/2021 | TARIK SAOUD |
| Building Plans Picked Up | 2/2/2021 | APPLICANT |
| Applicant returned to address corrections | 3/5/2021 | TARIK SAOUD |
| Plan Check Approved | 3/16/2021 | TARIK SAOUD |
| Issued | 4/16/2021 | APPLICANT |
| CofO in Progress | 5/26/2022 | JEFFREY PARD |
| Permit Finaled | 8/30/2022 | JOHN JANSON |
| CofO Issued | 8/30/2022 | JOHN JANSON |
| Permit Finaled | 8/30/2022 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/12/2021 | BARTON HOLMES |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 2/24/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/24/2021 | ADRIAN CASTRO |
Contact Information
| Architect | Diaz,, Enrique; Lic. No.: C33905 | 8309 EDMARU AVENUE WHITTIER, CA 90605 |
| Contractor | Owner-Builder | , |
| Engineer | Liu,, Frank Ying Chai; Lic. No.: C64806 | PO BOX 212 ARTESIA, CA 90702 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/17/2021 | Approved | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 5/24/2021 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/24/2021 | Approved | DAVID SCANTLIN |
| Pre-Inspection | 5/24/2021 | Approved | DAVID SCANTLIN |
| Deputy Reinf. Concrete | 5/25/2021 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2021 | Partial Approval | JEFFREY PARD |
| PLUMBING-Final | 6/23/2021 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 6/23/2021 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2021 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/3/2021 | Approved | JEFFREY PARD |
| Reinforced Concrete Frame | 8/9/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 8/13/2021 | Approved | JEFFREY PARD |
| Insulation | 8/24/2021 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Insulation | 8/26/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 9/8/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 11/17/2021 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 2/1/2022 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 2/1/2022 | Approved | JEFFREY PARD |
| Green Building Final | 2/1/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 2/1/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 2/1/2022 | Approved | JEFFREY PARD |
| HVAC-Final | 4/5/2022 | Approved | JEFFREY PARD |
| PLUMBING-Final | 4/5/2022 | Approved | JEFFREY PARD |
| Final | 5/25/2022 | OK to Issue CofO | JEFFREY PARD |