5912 W ERNEST AVE 90034

Certificate Information: 5912 W ERNEST AVE 90034

Application / Permit
20014-10000-05360
Plan Check / Job No.
B20LA22353
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE (2-STORY) “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 2/17/2022
Issuing Office
Current Status
CofO Issued on 8/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 CARLOS MONTES
Corrections Issued 1/14/2021 CARLOS MONTES
Quality Review Completed 2/2/2021 HERNAN ARREOLA
Applicant returned to address corrections 10/27/2021 CARLOS MONTES
Applicant returned to address corrections 12/16/2021 CARLOS MONTES
Applicant returned to address corrections 1/7/2022 CARLOS MONTES
Plan Check Approved 2/4/2022 CARLOS MONTES
Issued 2/17/2022 APPLICANT
CofO in Progress 8/10/2022 EVAN COOPER
Permit Finaled 8/26/2022 DANIEL ORRANTE
CofO Issued 8/26/2022 DANIEL ORRANTE
Permit Finaled 8/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/3/2021 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 2/9/2021 CECILIO NAVARRO
Construction near power lines Cleared 5/26/2021 RIDWAN HARDY
Sewer availability Cleared 9/13/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 10/25/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Rivera,, Bobby Zulueta; Lic. No.: C77218 14703 HELWIG AVE      NORWALK, CA 90650

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/3/2022 Corrections Issued EVAN COOPER
PLUMBING-Rough 3/11/2022 Partial Approval EVAN COOPER
Footing/Foundation/Slab 3/14/2022 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 4/1/2022 Conditional Approval EVAN COOPER
Wood Frame 4/5/2022 Partial Approval EVAN COOPER
Pre-Inspection 4/11/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 4/19/2022 Corrections Issued KENNETH NAGLE
Interior/Exterior Lathing 4/19/2022 Corrections Issued KENNETH NAGLE
ELECTRICAL-Rough 4/26/2022 Approved EVAN COOPER
HVAC-Rough 4/26/2022 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 4/26/2022 Partial Approval EVAN COOPER
PLUMBING-Rough 4/26/2022 Not Ready for Inspection EVAN COOPER
HVAC-Rough 4/28/2022 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 4/28/2022 Approved EVAN COOPER
Wood Frame 4/28/2022 Approved EVAN COOPER
Insulation 5/3/2022 Corrections Issued EVAN COOPER
Shower Pan 5/3/2022 Approved EVAN COOPER
Shower Pan 5/4/2022 Partial Approval KRISTEN CAUSEY
Drywall Nailing 5/6/2022 Approved EVAN COOPER
Green Building Rough 5/6/2022 Approved EVAN COOPER
Interior/Exterior Lathing 5/6/2022 Approved EVAN COOPER
Underground Mechanical 6/22/2022 Not Ready for Inspection KEVIN SARGSYAN
Pre-Inspection 6/27/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 6/30/2022 Approved EVAN COOPER
Final 6/30/2022 Not Ready for Inspection EVAN COOPER
Green Building Final 6/30/2022 Not Ready for Inspection EVAN COOPER
MERV13>=Final 6/30/2022 Not Ready for Inspection EVAN COOPER
MERV13>=Rough 6/30/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Not Ready EVAN COOPER
Service/Power Release 6/30/2022 Not Ready for Inspection EVAN COOPER
Smoke Detectors 6/30/2022 Not Ready for Inspection EVAN COOPER
Underground Mechanical 6/30/2022 Approved EVAN COOPER
Verify Sprinkler Sign Off 6/30/2022 Approved EVAN COOPER
Final 7/7/2022 Corrections Issued EVAN COOPER
Gas Test 7/7/2022 Corrections Issued EVAN COOPER
Green Building Final 7/7/2022 Approved EVAN COOPER
MERV13>=Final 7/7/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/7/2022 SGSOV Approved EVAN COOPER
Service/Power Release 7/7/2022 Not Ready for Inspection EVAN COOPER
Smoke Detectors 7/7/2022 Approved EVAN COOPER
Final 7/26/2022 Not Ready for Inspection MICHAEL PELHAM
ELECTRICAL-Final 8/9/2022 Approved EVAN COOPER
Final 8/9/2022 OK to Issue CofO EVAN COOPER
HVAC-Final 8/9/2022 Approved EVAN COOPER
PLUMBING-Final 8/9/2022 Approved EVAN COOPER
Service/Power Release 8/9/2022 Approved EVAN COOPER