3150 S PURDUE AVE 90066

Certificate Information: 3150 S PURDUE AVE 90066

Application / Permit
20014-10000-05353
Plan Check / Job No.
B20LA22324
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached garage to accessory dwelling unit with storage, gym and wine storage. New deck on grade at rear per LAMC 12.22 A.33 (c) and (d).
Permit Issued
Issued on 4/1/2021
Issuing Office
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 CELESTE MORRIS
Corrections Issued 1/12/2021 CELESTE MORRIS
Quality Review Completed 1/22/2021 PETER KIM
Building Plans Picked Up 1/26/2021 APPLICANT
Plan Check Approved 4/1/2021 CELESTE NGUYEN
Issued 4/1/2021 APPLICANT
CofO in Progress 2/16/2023 JOHNNY MIRANDA
Permit Finaled 2/16/2023 DANIEL ORRANTE
CofO Issued 2/16/2023 DANIEL ORRANTE
Permit Finaled 2/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 2/11/2021 JOHN BACON
Address approval Cleared 2/18/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 3/10/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 3/10/2021 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 3/11/2021 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 3/22/2021 BRIAN MILLER

Contact Information

Contractor Intension Construction Inc; Lic. No.: 956850-B 1378 CARMONA AVE      LOS ANGELES, CA 90019
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/14/2021 Partial Approval KEVIN SARGSYAN
Deputy Drilled-In Anchors 6/16/2021 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 6/17/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/23/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/30/2021 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 7/30/2021 Not Ready for Inspection OGANES TARAKHCHYAN
MERV13>=Rough 7/30/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/27/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/9/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Pre-Inspection 9/9/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/17/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 9/22/2021 Partial Approval EVAN COOPER
Underground Mechanical 9/22/2021 Partial Inspection EVAN COOPER
HVAC-Rough 9/24/2021 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 9/24/2021 Partial Approval OGANES TARAKHCHYAN
Sewer 9/24/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 9/24/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Sewer 9/29/2021 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 10/1/2021 Partial Approval EVAN COOPER
Green Building Rough 10/1/2021 Not Ready for Inspection EVAN COOPER
MERV13>=Rough 10/1/2021 Not Ready for Inspection EVAN COOPER
Sewer 10/1/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 10/29/2021 Not Ready for Inspection JOHNNY MIRANDA
Green Building Rough 10/29/2021 Not Ready for Inspection JOHNNY MIRANDA
MERV13>=Rough 10/29/2021 Not Ready for Inspection JOHNNY MIRANDA
Insulation 11/9/2021 Conditional Approval JOHNNY MIRANDA
Drywall Nailing 11/24/2021 Approved RYAN SALAZAR
Green Building Rough 11/24/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/24/2021 Approved RYAN SALAZAR
BUILDING-Rough-Frame 2/18/2022 Approved JOHNNY MIRANDA
MERV13>=Rough 2/18/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 5/12/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 6/6/2022 Approved JOHNNY MIRANDA
HVAC-Final 6/6/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 6/6/2022 Approved JOHNNY MIRANDA
Final 6/16/2022 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 6/16/2022 Approved JOHNNY MIRANDA
Green Building Final 6/16/2022 Approved JOHNNY MIRANDA
MERV13>=Final 6/16/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/16/2022 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 6/16/2022 Approved JOHNNY MIRANDA
Final 8/16/2022 Not Ready for Inspection JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 8/16/2022 SGSOV Not Ready JOHNNY MIRANDA
Final 8/22/2022 OK to Issue CofO JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 8/22/2022 SGSOV Approved JOHNNY MIRANDA