4032 N CARTWRIGHT AVE 91604

Certificate Information: 4032 N CARTWRIGHT AVE 91604

Application / Permit
20014-10000-05337
Plan Check / Job No.
B20LA22210
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVEERT (E) STORAGE TO ACCESSORY DWELLING UNIT WITH ADDITION AND ATTACHED NEW TRELLIS.
Permit Issued
Issued on 6/28/2021
Issuing Office
Current Status
CofO Issued on 5/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2020 APPLICANT
Assigned to Plan Check Engineer 12/11/2020 FARSHAD ALIMOHAMADI
Corrections Issued 12/12/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 2/25/2021 CRISTINA SALAZAR
Applicant returned to address corrections 4/28/2021 SAMUEL GONZALEZ
Plan Check Approved 5/19/2021 SAMUEL GONZALEZ
Building Plans Picked Up 6/8/2021 APPLICANT
Issued 6/28/2021 APPLICANT
CofO in Progress 12/30/2021 THOMAS FINNILA
CofO in Progress 12/30/2021 THOMAS FINNILA
Permit Finaled 5/7/2022 DANIEL ORRANTE
CofO Issued 5/7/2022 DANIEL ORRANTE
Permit Finaled 5/7/2022 DANIEL ORRANTE

Permit Application Clearance Information

ZI Cleared 1/20/2021 MAXFIELD VERMY
Address approval Cleared 1/21/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/21/2021 ADRIAN CASTRO
Sewer availability Cleared 1/22/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/17/2021 ADRIAN CASTRO

Contact Information

Contractor Sonora Construction Inc; Lic. No.: 965168-B 14411 KINGBURY ST      MISSION HILLS, CA 913452338
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/15/2021 Partial Inspection THOMAS FINNILA
PLUMBING-Rough 7/15/2021 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 7/20/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 7/20/2021 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 7/21/2021 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 8/11/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/11/2021 Not Ready for Inspection THOMAS FINNILA
Shower Pan 8/11/2021 Not Ready for Inspection THOMAS FINNILA
Wood Frame 8/11/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 8/17/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/17/2021 Partial Approval THOMAS FINNILA
Wood Frame 8/17/2021 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 9/8/2021 Approved THOMAS FINNILA
ELECTRICAL-Rough 9/8/2021 Approved THOMAS FINNILA
Green Building Rough 9/8/2021 Approved THOMAS FINNILA
MERV13>=Rough 9/8/2021 Approved THOMAS FINNILA
PLUMBING-Rough 9/8/2021 Conditional Approval THOMAS FINNILA
Insulation 9/24/2021 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 9/24/2021 Partial Approval LILIANA PORTILLO
Insulation 10/8/2021 Corrections Issued CALEB MEISTER
Interior/Exterior Lathing 10/8/2021 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 10/13/2021 Approved THOMAS FINNILA
Insulation 10/13/2021 Approved THOMAS FINNILA
Drywall Nailing 10/26/2021 Approved ALAN MORELOS
Wood Frame 10/26/2021 Approved ALAN MORELOS
ELECTRICAL-Final 12/15/2021 Not Ready for Inspection THOMAS FINNILA
Final 12/15/2021 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 12/15/2021 Approved THOMAS FINNILA
HVAC-Final 12/15/2021 Corrections Issued THOMAS FINNILA
PLUMBING-Final 12/15/2021 Approved THOMAS FINNILA
Final 12/20/2021 Corrections Issued THOMAS FINNILA
Green Building Final 12/20/2021 Approved THOMAS FINNILA
MERV13>=Final 12/20/2021 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/20/2021 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 12/20/2021 Approved THOMAS FINNILA
Final 12/27/2021 OK to Issue CofO THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/27/2021 SGSOV Approved THOMAS FINNILA