843 E MARCO PL 90291
Certificate Information: 843 E MARCO PL 90291
- Application / Permit
- 20014-10000-05331
- Plan Check / Job No.
- B20LA22192
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXITING GARAGE TO ADU WITH GARAGE PER 12.22 A33 C & D
- Permit Issued
- Issued on 6/23/2021
- Issuing Office
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | STARR CHEN |
| Corrections Issued | 12/20/2020 | STARR CHEN |
| Quality Review Completed | 1/7/2021 | HERNAN ARREOLA |
| Building Plans Picked Up | 1/11/2021 | APPLICANT |
| Applicant returned to address corrections | 3/9/2021 | STARR CHEN |
| Applicant returned to address corrections | 4/29/2021 | STARR CHEN |
| Applicant returned to address corrections | 5/13/2021 | STARR CHEN |
| Plan Check Approved | 6/23/2021 | STARR CHEN |
| Issued | 6/23/2021 | APPLICANT |
| CofO in Progress | 10/6/2023 | HERBERT GIRON |
| Permit Finaled | 10/24/2023 | DANIEL ORRANTE |
| CofO Issued | 10/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/21/2021 | MATTHEW CRAIG |
| Address approval | Cleared | 1/22/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 2/24/2021 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 3/11/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/16/2021 | DINAH GARIN |
| Construction near power lines | Cleared | 3/29/2021 | RIDWAN HARDY |
| Specific Plan | Cleared | 5/3/2021 | VALERIA CEJA |
| Coastal Zone | Cleared | 5/19/2021 | TERRI OSBORNE |
| Specific Plan | Cleared | 5/19/2021 | TERRI OSBORNE |
| City Hist. Cultural Monument | Cleared | 5/26/2021 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 5/26/2021 | LAMBERT GIESSINGER |
Contact Information
| Architect | Hamilton,, John Patrick; Lic. No.: C28865 | 12240 VENICE BLVD SUITE 25 LOS ANGELES, CA 90066 |
| Contractor | Lemette Construction Design; Lic. No.: 1044314-B | 3992 SANTA TOMAS NEWBURY PARK, CA 91320 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/21/2021 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/10/2021 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 8/11/2021 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/28/2021 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 1/13/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 1/13/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 1/13/2022 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 3/17/2022 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 3/29/2022 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 4/11/2022 | Conditional Approval | DAVID FEILER |
| Interior/Exterior Lathing | 4/11/2022 | Partial Approval | DAVID FEILER |
| Insulation | 4/18/2022 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 4/29/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 4/29/2022 | Approved | DAVID FEILER |
| Green Building Rough | 4/29/2022 | Approved | DAVID FEILER |
| Insulation | 4/29/2022 | Approved | DAVID FEILER |
| Shower Pan | 5/18/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/31/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/12/2023 | Approved | EVAN COOPER |
| Final | 6/12/2023 | Corrections Issued | EVAN COOPER |
| Green Building Final | 6/12/2023 | Approved | EVAN COOPER |
| HVAC-Final | 6/12/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 6/12/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 6/12/2023 | Approved | EVAN COOPER |
| Final | 7/7/2023 | Corrections Issued | EVAN COOPER |
| Final | 8/28/2023 | Corrections Issued | HERBERT GIRON |
| Final | 10/5/2023 | OK to Issue CofO | HERBERT GIRON |