2521 S VETERAN AVE 90064
Certificate Information: 2521 S VETERAN AVE 90064
- Application / Permit
- 20014-10000-05328
- Plan Check / Job No.
- B20LA22161
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SECOND STORY ADDITION AND MAJOR REMODEL TO SFD W/ATTACHED EXISTING GARAGE
- Permit Issued
- Issued on 6/4/2021
- Issuing Office
- Current Status
- CofO Issued on 5/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | TARIK SAOUD |
| Corrections Issued | 12/14/2020 | TARIK SAOUD |
| Quality Review Completed | 12/23/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/24/2021 | TARIK SAOUD |
| Building Plans Picked Up | 2/25/2021 | APPLICANT |
| Applicant returned to address corrections | 3/23/2021 | TARIK SAOUD |
| Plan Check Approved | 5/27/2021 | TARIK SAOUD |
| Issued | 6/4/2021 | APPLICANT |
| CofO in Progress | 5/9/2022 | JOHNNY MIRANDA |
| Permit Finaled | 5/16/2022 | DANIEL ORRANTE |
| CofO Issued | 5/16/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/16/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 1/19/2021 | LOUIS ORTEGA |
| Specific Plan | Cleared | 1/19/2021 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2021 | DINAH GARIN |
| Sewer availability | Cleared | 1/22/2021 | DINAH GARIN |
| Specific Plan | Cleared | 2/2/2021 | PEDRO AYALA |
| Grading Pre-Inspection | Cleared | 3/23/2021 | TARIK SAOUD |
| Low Impact Development | Cleared | 4/28/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/6/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/16/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/16/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 6/17/2021 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/25/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/29/2021 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 6/29/2021 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | Partial Approval | KENNETH NAGLE |
| Green Building Rough | 6/29/2021 | Not Ready for Inspection | KENNETH NAGLE |
| Green Building Rough | 6/29/2021 | Off-Hour Fees Due | |
| Deputy Steel/Welding | 7/2/2021 | Approved | DONALD GALLAGHER |
| BUILDING-Rough-Frame | 7/7/2021 | Not Ready for Inspection | DONALD GALLAGHER |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2021 | Partial Approval | DONALD GALLAGHER |
| Green Building Rough | 7/7/2021 | Not Ready for Inspection | DONALD GALLAGHER |
| Deputy Drilled-In Anchors | 7/23/2021 | Approved | DONALD GALLAGHER |
| ELECTRICAL-Rough | 8/11/2021 | Approved | EVAN COOPER |
| HVAC-Rough | 8/13/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/13/2021 | Approved | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 8/17/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/19/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2021 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 8/19/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/1/2021 | Partial Approval | MORRIS JACKSON |
| Insulation | 9/13/2021 | Approved | MORRIS JACKSON |
| Drywall Nailing | 9/17/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 9/17/2021 | Approved | MORRIS JACKSON |
| Gas Test | 2/1/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 2/1/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 2/4/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 2/8/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 2/17/2022 | Approved | OGANES TARAKHCHYAN |
| Special/Order Compliance | 2/28/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Final | 3/3/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/11/2022 | Approved | JOHNNY MIRANDA |
| Final | 3/11/2022 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/11/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 3/11/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 3/11/2022 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 3/14/2022 | Approved | JOHNNY MIRANDA |
| Final | 4/8/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 5/6/2022 | OK to Issue CofO | JOHNNY MIRANDA |