428-430 N HARVARD BLVD 90004

Certificate Information: 428-430 N HARVARD BLVD 90004

Application / Permit
20014-10000-05306
Plan Check / Job No.
B20LA22085
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
GROUND FLOOR ADDITION TO EXISTING DUPLEX. 1 OF 2
Permit Issued
Issued on 6/16/2021
Issuing Office
Current Status
CofO Issued on 12/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 JOE VO
Corrections Issued 12/19/2020 JOE VO
Quality Review Completed 12/31/2020 MINYE PAK
Applicant returned to address corrections 2/23/2021 JOE VO
Applicant returned to address corrections 3/14/2021 JOE VO
Applicant returned to address corrections 4/19/2021 JOE VO
Plan Check Approved 6/1/2021 JOE VO
Issued 6/16/2021 APPLICANT
Building Plans Picked Up 6/16/2021 APPLICANT
CofO in Progress 5/21/2022 SHAVONNE ESPINOZA
Permit Finaled 12/29/2022 DEROLD HAUFF
Permit Finaled 12/29/2022 DEROLD HAUFF
CofO Issued 12/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/7/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 1/13/2021 CECILIO NAVARRO
Sewer availability Cleared 1/13/2021 CECILIO NAVARRO
Tenant Habitability Plan Cleared 2/1/2021 PHILLIP MUNGUIA
Low Impact Development Cleared 5/14/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 5/14/2021 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/20/2021 Conditional Approval CHARLES BOGHOSKHAN
PLUMBING-Rough 7/23/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 7/28/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Partial Approval JOSEPH MCGARRY
Insulation 8/13/2021 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 9/3/2021 Corrections Issued CHRIS CHRISTENSEN
Deputy Wood Construction 9/10/2021 Conditional Approval CHARLES BOGHOSKHAN
Floor/Roof Diaphrgm/Shear Wall 9/13/2021 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 10/4/2021 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 10/14/2021 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/14/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 10/14/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 10/14/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 10/14/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/18/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 10/18/2021 Approved CHRIS CHRISTENSEN
Insulation 10/18/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 10/21/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 10/28/2021 Approved MASHEL JONGERT
Interior/Exterior Lathing 11/9/2021 Approved MASHEL JONGERT
ELECTRICAL-Final 1/18/2022 Corrections Issued CHRIS CHRISTENSEN
Final 1/18/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 1/18/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 1/18/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 1/18/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/18/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 1/18/2022 Approved CHRIS CHRISTENSEN
Final 2/9/2022 Not Ready for Inspection ARTHUR SARGSYAN
Green Building Final 2/9/2022 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/9/2022 SGSOV Not Ready ARTHUR SARGSYAN
Service/Power Release 2/14/2022 Corrections Issued SHAVONNE ESPINOZA
Service/Power Release 2/17/2022 Corrections Issued SHAVONNE ESPINOZA
ELECTRICAL-Final 2/24/2022 Approved CHRIS CHRISTENSEN
Green Building Final 2/24/2022 Approved CHRIS CHRISTENSEN
Service/Power Release 2/24/2022 Approved CHRIS CHRISTENSEN
Final 5/20/2022 OK to Issue CofO SHAVONNE ESPINOZA
SGSOV-Seismic Gas S/O Valve 5/20/2022 SGSOV Approved SHAVONNE ESPINOZA