532 W 113TH ST 90044
Certificate Information: 532 W 113TH ST 90044
- Application / Permit
- 20014-10000-05302
- Plan Check / Job No.
- B20LA22059
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED OF ADDITON OF TO THE (E) SFD AND TO OPEN A NEW EGRESS WINDOW. FOR (E) BEDROOM WITH ENGINEER DESIGN/DETAIL
- Permit Issued
- Issued on 5/26/2021
- Issuing Office
- Current Status
- CofO Issued on 7/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/11/2020 | RAHEL BEYENE |
| Corrections Issued | 12/30/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 2/23/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 3/17/2021 | SINA KHOSRAVI |
| Issued | 5/26/2021 | APPLICANT |
| Building Plans Picked Up | 6/2/2021 | APPLICANT |
| CofO in Progress | 6/28/2025 | DAVID FEILER |
| Permit Finaled | 7/9/2025 | RICHARD STEINBACH |
| CofO Issued | 7/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/4/2021 | CELINA MORENO |
| Sewer availability | Cleared | 3/4/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/25/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 7/12/2021 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 7/15/2021 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/11/2022 | Approved | JOHN KLARIN |
| Final | 2/11/2022 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 2/11/2022 | Approved | JOHN KLARIN |
| Green Building Final | 2/11/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 2/11/2022 | Approved | JOHN KLARIN |
| MERV13>=Final | 2/11/2022 | Approved | JOHN KLARIN |
| MERV13>=Rough | 2/11/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/11/2022 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 2/11/2022 | Approved | JOHN KLARIN |
| Final | 2/15/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 3/17/2025 | No Access for Inspection | BEN MOLSTAD |
| Final | 6/28/2025 | OK to Issue CofO | DAVID FEILER |