8846 W CASHIO ST 90035
Certificate Information: 8846 W CASHIO ST 90035
- Application / Permit
- 20014-10000-05300
- Plan Check / Job No.
- B20LA22046
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TWO-STORY ADDTITION AT REAR OF SFD
- Permit Issued
- Issued on 7/12/2021
- Issuing Office
- Current Status
- CofO Issued on 5/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/15/2021 | SINA KHOSRAVI |
| Corrections Issued | 2/22/2021 | SINA KHOSRAVI |
| Quality Review Completed | 3/2/2021 | STANLEY RAAP |
| Plan Check Approved | 6/22/2021 | SINA KHOSRAVI |
| Issued | 7/12/2021 | APPLICANT |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| CofO in Progress | 5/18/2023 | JEREMY TODD |
| Permit Finaled | 5/31/2023 | DANIEL ORRANTE |
| CofO Issued | 5/31/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/31/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2021 | DINAH GARIN |
| Sewer availability | Cleared | 3/23/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 3/26/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 6/22/2021 | SINA KHOSRAVI |
Contact Information
| Contractor | A R M Builders Inc; Lic. No.: 915352-B | 1080 S LA CIENEGA #311 LOS ANGELES, CA 90035 |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: C72927 | 560 31ST ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/31/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Barrier | 8/31/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 8/31/2021 | Not Ready for Inspection | EVAN COOPER |
| Underground Mechanical | 8/31/2021 | Not Ready for Inspection | EVAN COOPER |
| Pre-Inspection | 3/4/2022 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 4/1/2022 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 4/1/2022 | Approved | EVAN COOPER |
| METHANE-Subgrade | 4/1/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 4/29/2022 | Approved | EVAN COOPER |
| Deputy Wood Construction | 4/29/2022 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 4/29/2022 | Approved | EVAN COOPER |
| METHANE-Rough | 4/29/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 5/6/2022 | Approved | EVAN COOPER |
| Final | 6/1/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 6/1/2022 | Approved | EVAN COOPER |
| Green Building Final | 6/1/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/1/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 6/1/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 5/17/2023 | Approved | JEREMY TODD |
| Final | 5/17/2023 | OK to Issue CofO | JEREMY TODD |
| HVAC-Final | 5/17/2023 | Approved | JEREMY TODD |
| PLUMBING-Final | 5/17/2023 | Approved | JEREMY TODD |