1214 W 74TH ST 90044
Certificate Information: 1214 W 74TH ST 90044
- Application / Permit
- 20014-10000-05297
- Plan Check / Job No.
- B20LA22043
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADU ADDITION TO DETACHED GARAGE. DETACHED PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 10/29/2021
- Issuing Office
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | CARLOS MONTES |
| Corrections Issued | 1/15/2021 | CARLOS MONTES |
| Quality Review Completed | 2/3/2021 | WING SUEN |
| Plan Check Approved | 8/31/2021 | CARLOS MONTES |
| Issued | 10/29/2021 | APPLICANT |
| Building Plans Picked Up | 11/16/2021 | APPLICANT |
| CofO in Progress | 2/7/2023 | LILIANA PORTILLO |
| Permit Finaled | 2/14/2023 | DEROLD HAUFF |
| CofO Issued | 2/14/2023 | DEROLD HAUFF |
| Permit Finaled | 2/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2021 | JEANIE LAM |
| Sewer availability | Cleared | 3/3/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2021 | JEANIE LAM |
| Low Impact Development | Cleared | 7/28/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/29/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/17/2021 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 2/17/2022 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/25/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/28/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/3/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 4/8/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/21/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 4/21/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 5/5/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/9/2022 | Conditional Approval | LILIANA PORTILLO |
| Green Building Rough | 5/9/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 5/9/2022 | Approved | LILIANA PORTILLO |
| Insulation | 5/17/2022 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 6/14/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 6/14/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 7/8/2022 | Partial Approval | LILIANA PORTILLO |
| Green Building Rough | 8/10/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/10/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/19/2022 | Corrections Issued | SCOTT FINNILA |
| Drywall Nailing | 10/19/2022 | Partial Approval | SCOTT FINNILA |
| Final | 10/19/2022 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 10/19/2022 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 10/19/2022 | SGSOV Not Ready | SCOTT FINNILA |
| Smoke Detectors | 10/19/2022 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 10/31/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/31/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/31/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 10/31/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 10/31/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 10/31/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 10/31/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/8/2022 | Approved | LILIANA PORTILLO |
| Final | 11/8/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 11/8/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 11/8/2022 | Approved | LILIANA PORTILLO |
| Service/Power Release | 11/8/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 12/19/2022 | Conditional Approval | LILIANA PORTILLO |
| Final | 1/10/2023 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 1/23/2023 | Approved | SABAS ALONSO |
| Special/Order Compliance | 1/23/2023 | Partial Inspection | LILIANA PORTILLO |
| Final | 1/30/2023 | Corrections Issued | STUART CHAPMAN |
| Final | 2/6/2023 | OK to Issue CofO | LILIANA PORTILLO |