2425 N DALY ST 90031

Certificate Information: 2425 N DALY ST 90031

Application / Permit
20014-10000-05294
Plan Check / Job No.
B20LA22033
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
Addition to existing 705.3 sf Type V, 1-Story restaurant building. Facade on Daly to be Facace on Daly St to be remodeled, new outdoor dining araa. Hours of operation are per approved Case No. ZA-2020-4644-CUB-CDO from 9am-11pm Monday thru Thrusday; 9am-12am, Friday and Saturday; and 9am to 10:30pm, Sunday.
Permit Issued
Issued on 9/28/2021
Issuing Office
Current Status
CofO Issued on 1/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 SALVADOR QUINTANILLA
Corrections Issued 1/19/2021 SALVADOR QUINTANILLA
Quality Review Completed 1/22/2021 PETER KIM
Building Plans Picked Up 1/28/2021 APPLICANT
Disabled Access Plans Picked Up 1/29/2021 APPLICANT
Applicant returned to address corrections 2/3/2021 SALVADOR QUINTANILLA
Applicant returned to address corrections 2/17/2021 SALVADOR QUINTANILLA
Applicant returned to address corrections 3/24/2021 SALVADOR QUINTANILLA
Applicant returned to address corrections 3/25/2021 SALVADOR QUINTANILLA
Applicant returned to address corrections 4/28/2021 SALVADOR QUINTANILLA
Applicant returned to address corrections 5/27/2021 SALVADOR QUINTANILLA
Applicant returned to address corrections 6/16/2021 SALVADOR QUINTANILLA
Plan Check Approved 9/2/2021 SALVADOR QUINTANILLA
Issued 9/28/2021 APPLICANT
Green Plans Picked Up 1/30/2023 APPLICANT
CofO in Progress 12/12/2024 RAMAZANALI ALMASI
Permit Finaled 1/31/2025 ERNESTO CORRAL
CofO Issued 1/31/2025 ERNESTO CORRAL
Permit Finaled 1/31/2025 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 1/15/2021 NEGAR NEJAD
Food establishment approval Cleared 1/27/2021 LACDHS APPROVED
Eng Process Fee Ord 176,300 Cleared 2/22/2021 CECILIO NAVARRO
Food Service Establishment Cleared 2/25/2021 PAWAN VERMA
Sewer availability Cleared 3/12/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 3/31/2021 CECILIO NAVARRO
Highway dedication Cleared 4/15/2021 CECILIO NAVARRO
DAS Clearance Cleared 6/23/2021 SALVADOR QUINTANILLA
Supp. Use District POD/CDO/TDO Cleared 8/11/2021 MINDY NGUYEN
ZA Case Cleared 8/11/2021 MINDY NGUYEN
ZA Case Cleared 8/11/2021 MINDY NGUYEN
ZI Cleared 8/11/2021 MINDY NGUYEN
"Q" conditions Cleared 8/25/2021 MINDY NGUYEN
Comm Cor/Mini-Mall Cleared 8/25/2021 MINDY NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 1551 RANDALL ST      GLENDALE, CA 91201

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 1/25/2022 Partial Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 8/3/2022 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 8/3/2022 Not Ready for Inspection MARK FERRARI
Excavation/Setback/Form/Re-Bar 9/9/2022 Partial Approval MARK FERRARI
Footing/Foundation/Slab 9/9/2022 Partial Approval MARK FERRARI
Masonry Wall/Backfill 9/21/2022 Corrections Issued MARK FERRARI
Deputy Reinf. Masonry 9/28/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 10/4/2022 Corrections Issued RAFAEL ESPINOZA
Green Building Rough 10/11/2022 Not Ready for Inspection MARK FERRARI
Wood Frame 10/11/2022 Partial Inspection MARK FERRARI
Green Building Rough 10/13/2022 Not Ready for Inspection MARK FERRARI
Masonry Wall/Backfill 10/13/2022 Partial Approval MARK FERRARI
Wood Frame 10/13/2022 Partial Approval MARK FERRARI
Deputy Steel/Welding 10/27/2022 Conditional Approval MARK FERRARI
Green Building Rough 10/27/2022 Not Ready for Inspection MARK FERRARI
Wood Frame 10/27/2022 Partial Inspection MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Partial Approval MARK FERRARI
Green Building Rough 11/4/2022 Partial Inspection MARK FERRARI
Wood Frame 11/4/2022 Partial Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Approved MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Not Ready for Inspection MARK FERRARI
Masonry Wall/Backfill 11/18/2022 Partial Approval MARK FERRARI
Masonry Wall/Backfill 11/29/2022 Order to Comply Issued MARK FERRARI
Green Building Rough 1/20/2023 No Access for Inspection RAFAEL CORTES
Wood Frame 1/20/2023 No Access for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 1/24/2023 No Access for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 1/26/2023 Approved RAMAZANALI ALMASI
Green Building Rough 1/26/2023 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 1/26/2023 Partial Approval RAMAZANALI ALMASI
Insulation 2/28/2023 Conditional Approval VAHE KELEDJIAN
Drywall Nailing 3/8/2023 Partial Approval JEROME BLACKWOOD
Interior/Exterior Lathing 3/31/2023 Approved JULIAN CAPUCETTI
Excavation/Setback/Form/Re-Bar 5/8/2023 Approved JULIAN CAPUCETTI
Final 4/26/2024 Not Ready for Inspection RAMAZANALI ALMASI
Footing/Foundation/Slab 4/26/2024 Approved RAMAZANALI ALMASI
Green Building Final 4/26/2024 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Rough 4/26/2024 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Approved RAMAZANALI ALMASI
Smoke Detectors 4/26/2024 Approved RAMAZANALI ALMASI
Wood Frame 4/26/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 5/14/2024 Not Ready for Inspection RONALD JIMENEZ
Green Building Final 5/14/2024 Approved RONALD JIMENEZ
Green Building Rough 5/14/2024 Approved RONALD JIMENEZ
Wood Frame 5/14/2024 Approved RONALD JIMENEZ
Final 5/16/2024 Not Ready for Inspection RAMAZANALI ALMASI
Pre-Inspection 5/16/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 5/22/2024 Conditional Approval RAMAZANALI ALMASI
Final 12/12/2024 OK to Issue CofO RAMAZANALI ALMASI
Special/Order Compliance 1/30/2025 Approved RAMAZANALI ALMASI