2425 N DALY ST 90031
Certificate Information: 2425 N DALY ST 90031
- Application / Permit
- 20014-10000-05294
- Plan Check / Job No.
- B20LA22033
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Addition to existing 705.3 sf Type V, 1-Story restaurant building. Facade on Daly to be Facace on Daly St to be remodeled, new outdoor dining araa. Hours of operation are per approved Case No. ZA-2020-4644-CUB-CDO from 9am-11pm Monday thru Thrusday; 9am-12am, Friday and Saturday; and 9am to 10:30pm, Sunday.
- Permit Issued
- Issued on 9/28/2021
- Issuing Office
- Current Status
- CofO Issued on 1/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | SALVADOR QUINTANILLA |
| Corrections Issued | 1/19/2021 | SALVADOR QUINTANILLA |
| Quality Review Completed | 1/22/2021 | PETER KIM |
| Building Plans Picked Up | 1/28/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 1/29/2021 | APPLICANT |
| Applicant returned to address corrections | 2/3/2021 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 2/17/2021 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 3/24/2021 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 3/25/2021 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 4/28/2021 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 5/27/2021 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 6/16/2021 | SALVADOR QUINTANILLA |
| Plan Check Approved | 9/2/2021 | SALVADOR QUINTANILLA |
| Issued | 9/28/2021 | APPLICANT |
| Green Plans Picked Up | 1/30/2023 | APPLICANT |
| CofO in Progress | 12/12/2024 | RAMAZANALI ALMASI |
| Permit Finaled | 1/31/2025 | ERNESTO CORRAL |
| CofO Issued | 1/31/2025 | ERNESTO CORRAL |
| Permit Finaled | 1/31/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 1/15/2021 | NEGAR NEJAD |
| Food establishment approval | Cleared | 1/27/2021 | LACDHS APPROVED |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | CECILIO NAVARRO |
| Food Service Establishment | Cleared | 2/25/2021 | PAWAN VERMA |
| Sewer availability | Cleared | 3/12/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 3/31/2021 | CECILIO NAVARRO |
| Highway dedication | Cleared | 4/15/2021 | CECILIO NAVARRO |
| DAS Clearance | Cleared | 6/23/2021 | SALVADOR QUINTANILLA |
| Supp. Use District POD/CDO/TDO | Cleared | 8/11/2021 | MINDY NGUYEN |
| ZA Case | Cleared | 8/11/2021 | MINDY NGUYEN |
| ZA Case | Cleared | 8/11/2021 | MINDY NGUYEN |
| ZI | Cleared | 8/11/2021 | MINDY NGUYEN |
| "Q" conditions | Cleared | 8/25/2021 | MINDY NGUYEN |
| Comm Cor/Mini-Mall | Cleared | 8/25/2021 | MINDY NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 1551 RANDALL ST GLENDALE, CA 91201 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 1/25/2022 | Partial Inspection | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 8/3/2022 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 8/3/2022 | Not Ready for Inspection | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 9/9/2022 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 9/9/2022 | Partial Approval | MARK FERRARI |
| Masonry Wall/Backfill | 9/21/2022 | Corrections Issued | MARK FERRARI |
| Deputy Reinf. Masonry | 9/28/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Masonry | 10/3/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Masonry Wall/Backfill | 10/4/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Green Building Rough | 10/11/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 10/11/2022 | Partial Inspection | MARK FERRARI |
| Green Building Rough | 10/13/2022 | Not Ready for Inspection | MARK FERRARI |
| Masonry Wall/Backfill | 10/13/2022 | Partial Approval | MARK FERRARI |
| Wood Frame | 10/13/2022 | Partial Approval | MARK FERRARI |
| Deputy Steel/Welding | 10/27/2022 | Conditional Approval | MARK FERRARI |
| Green Building Rough | 10/27/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 10/27/2022 | Partial Inspection | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2022 | Partial Approval | MARK FERRARI |
| Green Building Rough | 11/4/2022 | Partial Inspection | MARK FERRARI |
| Wood Frame | 11/4/2022 | Partial Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Approved | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Not Ready for Inspection | MARK FERRARI |
| Masonry Wall/Backfill | 11/18/2022 | Partial Approval | MARK FERRARI |
| Masonry Wall/Backfill | 11/29/2022 | Order to Comply Issued | MARK FERRARI |
| Green Building Rough | 1/20/2023 | No Access for Inspection | RAFAEL CORTES |
| Wood Frame | 1/20/2023 | No Access for Inspection | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 1/24/2023 | No Access for Inspection | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 1/26/2023 | Approved | RAMAZANALI ALMASI |
| Green Building Rough | 1/26/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 1/26/2023 | Partial Approval | RAMAZANALI ALMASI |
| Insulation | 2/28/2023 | Conditional Approval | VAHE KELEDJIAN |
| Drywall Nailing | 3/8/2023 | Partial Approval | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 3/31/2023 | Approved | JULIAN CAPUCETTI |
| Excavation/Setback/Form/Re-Bar | 5/8/2023 | Approved | JULIAN CAPUCETTI |
| Final | 4/26/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 4/26/2024 | Approved | RAMAZANALI ALMASI |
| Green Building Final | 4/26/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Rough | 4/26/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Approved | RAMAZANALI ALMASI |
| Smoke Detectors | 4/26/2024 | Approved | RAMAZANALI ALMASI |
| Wood Frame | 4/26/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 5/14/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Green Building Final | 5/14/2024 | Approved | RONALD JIMENEZ |
| Green Building Rough | 5/14/2024 | Approved | RONALD JIMENEZ |
| Wood Frame | 5/14/2024 | Approved | RONALD JIMENEZ |
| Final | 5/16/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Pre-Inspection | 5/16/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 5/22/2024 | Conditional Approval | RAMAZANALI ALMASI |
| Final | 12/12/2024 | OK to Issue CofO | RAMAZANALI ALMASI |
| Special/Order Compliance | 1/30/2025 | Approved | RAMAZANALI ALMASI |