710 N BROOKTREE ROAD 90272
Certificate Information: 710 N BROOKTREE ROAD 90272
- Application / Permit
- 20014-10000-05293
- Plan Check / Job No.
- B20LA22030
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- RENOVATION OF EXISTING 2 STORY 2,752 SF SINGLE FAMILY DWELLING AND 462 SF 2ND FLOOR ADDITION
- Permit Issued
- Issued on 4/26/2021
- Issuing Office
- Current Status
- CofO Issued on 11/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | FELIPE HERNANDEZ |
| Corrections Issued | 12/15/2020 | FELIPE HERNANDEZ |
| Quality Review Completed | 12/29/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 1/21/2021 | FELIPE HERNANDEZ |
| Building Plans Picked Up | 1/22/2021 | APPLICANT |
| Plan Check Approved | 4/16/2021 | FELIPE HERNANDEZ |
| Issued | 4/26/2021 | APPLICANT |
| CofO in Progress | 11/17/2023 | ARAM AVEDISIAN |
| Permit Finaled | 11/21/2023 | DANIEL ORRANTE |
| CofO Issued | 11/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/15/2021 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2021 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 1/19/2021 | NIKTA MOUSAVI |
| Grading Pre-Inspection | Cleared | 1/21/2021 | MANUEL TEJADA |
| Miscellaneous | Cleared | 2/3/2021 | JENSON LEE |
| Hydrant and Access approval | Cleared | 2/5/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/6/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/9/2021 | MAHELET GEBEYHU |
| Watercourse | Cleared | 4/9/2021 | MAHELET GEBEYHU |
Contact Information
| Contractor | Drexler Mark & Associates Inc; Lic. No.: 794343-B | 25876 THE OLD ROAD #548 VALENCIA, CA 91381 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/19/2021 | Partial Approval | JOHN KIDWELL |
| FLOOD-Elevation Certificate | 5/24/2021 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/24/2021 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 6/17/2021 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 6/24/2021 | Conditional Approval | AMY COLIN |
| Footing/Foundation/Slab | 6/30/2021 | Corrections Issued | JOHN KIDWELL |
| PLUMBING-Rough | 6/30/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Underground Mechanical | 6/30/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 7/2/2021 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 7/8/2021 | Conditional Approval | JACK MATTILLO |
| Deputy Drilled-In Anchors | 7/28/2021 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/29/2021 | Partial Approval | KENNETH NAGLE |
| PLUMBING-Rough | 7/29/2021 | Partial Approval | KENNETH NAGLE |
| Deputy Steel/Welding | 9/23/2021 | Conditional Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 11/1/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 11/4/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Corrections Issued | JOHN KIDWELL |
| Deputy Wood Construction | 12/6/2021 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 5/4/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/3/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 6/10/2022 | Approved | MICHAEL PELHAM |
| Underground Mechanical | 6/16/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 10/25/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 10/25/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 10/27/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/28/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 11/14/2022 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 11/21/2022 | Partial Approval | JUAN VALENZUELA |
| HVAC-Rough | 11/21/2022 | Partial Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 11/21/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/23/2022 | Approved | CARLOS MATAMOROS |
| FLOOD-Elevation Certificate | 11/23/2022 | Approved | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 11/23/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 11/23/2022 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 11/23/2022 | Approved | CARLOS MATAMOROS |
| Insulation | 12/5/2022 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 12/23/2022 | Approved | KEVIN SARGSYAN |
| Shower Pan | 2/3/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Shower Pan | 2/7/2023 | Approved | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 3/8/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/14/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 3/15/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Service/Power Release | 7/7/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/14/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/2/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 8/4/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 8/9/2023 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/16/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 8/16/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/16/2023 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 8/16/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/16/2023 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/16/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 8/31/2023 | No Access for Inspection | KENNETH NAGLE |
| Final | 11/17/2023 | OK to Issue CofO | ARAM AVEDISIAN |