2033 N HERCULES DR 90046

Certificate Information: 2033 N HERCULES DR 90046

Application / Permit
20014-10000-05258
Plan Check / Job No.
B20LA21957
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODELING OF SFD/GARAGE
Permit Issued
Issued on 2/11/2021
Issuing Office
Current Status
CofO Issued on 2/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 MAHNAZ NOURHASHEMI
Corrections Issued 1/7/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 1/7/2021 TIEN JEN WANG
Building Plans Picked Up 1/11/2021 APPLICANT
Applicant returned to address corrections 2/8/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 2/11/2021 MAHNAZ NOURHASHEMI
Issued 2/11/2021 APPLICANT
CofO in Progress 2/16/2022 RAUL BARAJAS
Permit Finaled 2/16/2022 DEROLD HAUFF
CofO Issued 2/16/2022 DEROLD HAUFF
Permit Finaled 2/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/21/2021 THOMAS LANG
Sewer availability Cleared 1/22/2021 RENZ SORIANO
Grading Pre-Inspection Cleared 1/27/2021 PATRICK MISCHLICH

Contact Information

Architect Migliozzi,, Jorgelina Eliana; Lic. No.: C35585 31861 VIA PAVO REAL      COTO DE CAZA, CA 92679
Contractor Milex Builders Inc; Lic. No.: 1057655-B 19 HEARTHSIDE RD      LADERA RANCH, CA 92694

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/23/2021 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 3/2/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 3/2/2021 Partial Approval RAUL BARAJAS
Sewer 3/2/2021 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/5/2021 Partial Inspection RAUL BARAJAS
Footing/Foundation/Slab 3/8/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 3/12/2021 Partial Approval RAUL BARAJAS
Shower Pan 3/12/2021 Approved RAUL BARAJAS
Drywall Nailing 3/17/2021 Partial Approval RAUL BARAJAS
Deputy Steel/Welding 4/1/2021 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 5/6/2021 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 5/6/2021 Partial Approval JOSEPH MCGARRY
HVAC-Rough 5/6/2021 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 5/6/2021 Partial Approval JOSEPH MCGARRY
Structural Steel Frame 5/6/2021 Approved JOSEPH MCGARRY
Deputy Wood Construction 5/20/2021 Conditional Approval BRIAN SULLIVAN
Deputy Wood Construction 5/25/2021 Conditional Approval RAUL BARAJAS
Insulation 5/26/2021 Approved RAUL BARAJAS
Shower Pan 5/26/2021 Approved RAUL BARAJAS
Drywall Nailing 6/1/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 8/4/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 1/12/2022 Approved RAUL BARAJAS
Final 1/12/2022 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 1/12/2022 SGSOV Approved RAUL BARAJAS
Smoke Detectors 1/12/2022 Approved RAUL BARAJAS
Final 1/26/2022 OK to Issue CofO RAUL BARAJAS