6506-6508 N OAKDALE AVE 91367

Certificate Information: 6506-6508 N OAKDALE AVE 91367

Application / Permit
20014-10000-05231
Plan Check / Job No.
B20LA21867
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*ePLAN CHECK* Convert portion (243 SF) of (E) SFD and (E) attached garage (385 SF) to Accessory Dwelling Unit per LAMC 12.22A33(c)-(d) with one-story addition to ADU (51 SF), creating a one-story Single Family Dwelling (1,352 SF) with attached ADU (679 SQ FT). Scope of work to include partial roof framing replacement per engineered design.
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 8/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2020 APPLICANT
Assigned to Plan Check Engineer 12/1/2020 LAMAR DAVIS
Corrections Issued 12/1/2020 LAMAR DAVIS
Applicant returned to address corrections 3/31/2021 LAMAR DAVIS
Plan Check Approved 4/13/2021 LAMAR DAVIS
Issued 4/22/2021 APPLICANT
CofO in Progress 8/26/2022 STEVEN BACK
Permit Finaled 8/30/2022 JOHN JANSON
CofO Issued 8/30/2022 JOHN JANSON
Permit Finaled 8/30/2022 JOHN JANSON

Permit Application Clearance Information

ZI Cleared 1/7/2021 DANG NGUYEN
Low Impact Development Cleared 3/11/2021 MARTIN FRAGOSO
Address approval Cleared 3/22/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 3/22/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/23/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/23/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/14/2021 Corrections Issued HENRY KIM
Pre-Inspection 9/14/2021 Partial Inspection RYAN SALAZAR
PLUMBING-Rough 9/23/2021 Corrections Issued HENRY KIM
Pre-Inspection 9/23/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 11/16/2021 Corrections Issued STEVEN BACK
Deputy Drilled-In Anchors 11/22/2021 Conditional Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 11/29/2021 Approved STEVEN BACK
Footing/Foundation/Slab 11/29/2021 Approved STEVEN BACK
PLUMBING-Rough 11/29/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 1/7/2022 Corrections Issued STEVEN BACK
Pre-Inspection 1/7/2022 Partial Inspection STEVEN BACK
ELECTRICAL-Rough 1/26/2022 Corrections Issued STEVEN BACK
HVAC-Rough 1/26/2022 Corrections Issued STEVEN BACK
PLUMBING-Rough 1/26/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 2/4/2022 Approved STEVEN BACK
HVAC-Rough 2/4/2022 Approved STEVEN BACK
PLUMBING-Rough 2/4/2022 Approved STEVEN BACK
Sewer 2/4/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/8/2022 Corrections Issued STEVEN BACK
Deputy Wood Construction 2/9/2022 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 2/11/2022 No Access for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 No Access for Inspection STEVEN BACK
Green Building Rough 2/11/2022 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 3/4/2022 Approved STEVEN BACK
Drywall Nailing 3/4/2022 Corrections Issued STEVEN BACK
Green Building Rough 3/4/2022 Approved STEVEN BACK
Insulation 3/4/2022 Approved STEVEN BACK
Interior/Exterior Lathing 3/4/2022 Partial Approval STEVEN BACK
Shower Pan 3/4/2022 Approved STEVEN BACK
Drywall Nailing 3/17/2022 Approved STEVEN BACK
Interior/Exterior Lathing 3/17/2022 Approved STEVEN BACK
ELECTRICAL-Rough 5/5/2022 Corrections Issued STEVEN BACK
ELECTRICAL-Final 8/16/2022 Not Ready for Inspection STEVEN BACK
Final 8/16/2022 Corrections Issued STEVEN BACK
Green Building Final 8/16/2022 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/16/2022 SGSOV Not Ready STEVEN BACK
Smoke Detectors 8/16/2022 Corrections Issued STEVEN BACK
Final 8/26/2022 OK to Issue CofO STEVEN BACK
Green Building Final 8/26/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/26/2022 SGSOV Approved STEVEN BACK
Smoke Detectors 8/26/2022 Approved STEVEN BACK