9905 S BANDERA ST 90002

Certificate Information: 9905 S BANDERA ST 90002

Application / Permit
20014-10000-05224
Plan Check / Job No.
B20LA21853
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD AT REAR
Permit Issued
Issued on 3/22/2021
Issuing Office
Current Status
CofO Issued on 8/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2020 APPLICANT
Assigned to Plan Check Engineer 12/9/2020 RACHEL BEYENE
Corrections Issued 12/10/2020 RACHEL BEYENE
Plan Check Approved 3/19/2021 FERNANDO FLORES
Issued 3/22/2021 APPLICANT
Building Plans Picked Up 3/26/2021 APPLICANT
CofO in Progress 7/23/2021 CRAIG DAVIS
Permit Finaled 8/14/2021 DEROLD HAUFF
CofO Issued 8/14/2021 DEROLD HAUFF
Permit Finaled 8/14/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/23/2020 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 12/30/2020 ROSA SILVA
Sewer availability Cleared 2/4/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/19/2021 Corrections Issued EUGENE CASSIDY
Insulation 4/30/2021 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 5/12/2021 Corrections Issued EUGENE CASSIDY
Green Building Rough 5/12/2021 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/17/2021 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 5/20/2021 Conditional Approval JESUS PINEDA
ELECTRICAL-Rough 5/20/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 5/20/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 5/24/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 5/24/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 5/24/2021 Approved EUGENE CASSIDY
Insulation 5/27/2021 Approved JESUS PINEDA
BUILDING-Rough-Frame 6/1/2021 Approved EUGENE CASSIDY
Drywall Nailing 6/1/2021 Approved EUGENE CASSIDY
Green Building Rough 6/1/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 6/1/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 6/9/2021 Approved EUGENE CASSIDY
Shower Pan 6/9/2021 Approved EUGENE CASSIDY
Final 7/12/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/12/2021 Approved EUGENE CASSIDY
Green Building Final 7/12/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 7/12/2021 Not Ready for Inspection EUGENE CASSIDY
Final 7/16/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 7/16/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/16/2021 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 7/16/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 7/22/2021 Approved EUGENE CASSIDY
Final 7/22/2021 OK to Issue CofO EUGENE CASSIDY
Green Building Final 7/22/2021 Approved EUGENE CASSIDY
HVAC-Final 7/22/2021 Approved EUGENE CASSIDY
PLUMBING-Final 7/22/2021 Approved EUGENE CASSIDY
Smoke Detectors 7/22/2021 Approved EUGENE CASSIDY