2208 N WILLETTA AVE 90068

Certificate Information: 2208 N WILLETTA AVE 90068

Application / Permit
20014-10000-05223
Plan Check / Job No.
B20LA21850
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION TO (E) 2-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 11/2/2021
Issuing Office
Current Status
CofO Issued on 7/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 DANIEL YIP
Corrections Issued 12/8/2020 DANIEL YIP
Quality Review Completed 12/17/2020 ALLEN MANALANSAN
Applicant returned to address corrections 8/12/2021 DANIEL YIP
Applicant returned to address corrections 10/20/2021 DANIEL YIP
Plan Check Approved 10/26/2021 DANIEL YIP
Issued 11/2/2021 APPLICANT
Building Plans Picked Up 11/5/2021 APPLICANT
CofO in Progress 6/26/2023 BRIAN SULLIVAN
No Progress 6/30/2023 BRIAN SULLIVAN
CofO in Progress 7/17/2023 BRIAN SULLIVAN
Permit Finaled 7/30/2023 DEROLD HAUFF
CofO Issued 7/30/2023 DEROLD HAUFF
Permit Finaled 7/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/11/2021 BRIAN MILLER
BHO/Hillside ordinance Cleared 6/14/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 6/14/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/15/2021 CELINA MORENO
ZA Case Cleared 8/3/2021 MARITZA PRZEKOP
GPI Written Notices Cleared 8/12/2021 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/4/2022 Approved RAUL BARAJAS
BUILDING-Rough-Frame 6/9/2022 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Partial Approval RYAN SALAZAR
Green Building Rough 6/9/2022 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 7/12/2022 Corrections Issued RUBEN SALAS
ELECTRICAL-Rough 7/12/2022 Approved RUBEN SALAS
Green Building Rough 7/12/2022 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 7/12/2022 Approved RUBEN SALAS
Wood Frame 7/12/2022 Not Ready for Inspection RUBEN SALAS
Deputy Wood Construction 7/14/2022 Conditional Approval RYAN SALAZAR
Drywall Nailing 8/3/2022 Conditional Approval SCOTT FINNILA
Green Building Rough 8/3/2022 Partial Approval SCOTT FINNILA
Shower Pan 8/3/2022 Approved SCOTT FINNILA
BUILDING-Rough-Frame 8/8/2022 Conditional Approval SCOTT FINNILA
Green Building Rough 8/8/2022 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Approved RUBEN SALAS
Interior/Exterior Lathing 12/1/2022 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 3/20/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 3/20/2023 Approved JOAQUIN GREENOUGH
Final 3/20/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/20/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 3/20/2023 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 3/20/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 3/20/2023 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/4/2023 No Access for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Final 4/4/2023 No Access for Inspection JOAQUIN GREENOUGH
Final 4/4/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/4/2023 No Access for Inspection JOAQUIN GREENOUGH
Green Building Final 4/4/2023 No Access for Inspection JOAQUIN GREENOUGH
PLUMBING-Final 4/4/2023 No Access for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 4/4/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 4/4/2023 No Access for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/10/2023 Approved BRIAN SULLIVAN
Final 4/10/2023 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 4/10/2023 Approved BRIAN SULLIVAN
Green Building Final 4/10/2023 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 4/10/2023 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 4/10/2023 Approved BRIAN SULLIVAN
Final 6/26/2023 OK to Issue CofO BRIAN SULLIVAN