2208 N WILLETTA AVE 90068
Certificate Information: 2208 N WILLETTA AVE 90068
- Application / Permit
- 20014-10000-05223
- Plan Check / Job No.
- B20LA21850
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION TO (E) 2-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- CofO Issued on 7/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | DANIEL YIP |
| Corrections Issued | 12/8/2020 | DANIEL YIP |
| Quality Review Completed | 12/17/2020 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 8/12/2021 | DANIEL YIP |
| Applicant returned to address corrections | 10/20/2021 | DANIEL YIP |
| Plan Check Approved | 10/26/2021 | DANIEL YIP |
| Issued | 11/2/2021 | APPLICANT |
| Building Plans Picked Up | 11/5/2021 | APPLICANT |
| CofO in Progress | 6/26/2023 | BRIAN SULLIVAN |
| No Progress | 6/30/2023 | BRIAN SULLIVAN |
| CofO in Progress | 7/17/2023 | BRIAN SULLIVAN |
| Permit Finaled | 7/30/2023 | DEROLD HAUFF |
| CofO Issued | 7/30/2023 | DEROLD HAUFF |
| Permit Finaled | 7/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/11/2021 | BRIAN MILLER |
| BHO/Hillside ordinance | Cleared | 6/14/2021 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 6/14/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2021 | CELINA MORENO |
| ZA Case | Cleared | 8/3/2021 | MARITZA PRZEKOP |
| GPI Written Notices | Cleared | 8/12/2021 | DANIEL YIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/4/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/9/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 6/9/2022 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 7/12/2022 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Rough | 7/12/2022 | Approved | RUBEN SALAS |
| Green Building Rough | 7/12/2022 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 7/12/2022 | Approved | RUBEN SALAS |
| Wood Frame | 7/12/2022 | Not Ready for Inspection | RUBEN SALAS |
| Deputy Wood Construction | 7/14/2022 | Conditional Approval | RYAN SALAZAR |
| Drywall Nailing | 8/3/2022 | Conditional Approval | SCOTT FINNILA |
| Green Building Rough | 8/3/2022 | Partial Approval | SCOTT FINNILA |
| Shower Pan | 8/3/2022 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/8/2022 | Conditional Approval | SCOTT FINNILA |
| Green Building Rough | 8/8/2022 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 12/1/2022 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/20/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Drywall Nailing | 3/20/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 3/20/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 3/20/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 3/20/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 3/20/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 3/20/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/4/2023 | No Access for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 4/4/2023 | No Access for Inspection | JOAQUIN GREENOUGH |
| Final | 4/4/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 4/4/2023 | No Access for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 4/4/2023 | No Access for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 4/4/2023 | No Access for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 4/4/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 4/4/2023 | No Access for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/10/2023 | Approved | BRIAN SULLIVAN |
| Final | 4/10/2023 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 4/10/2023 | Approved | BRIAN SULLIVAN |
| Green Building Final | 4/10/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2023 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 4/10/2023 | Approved | BRIAN SULLIVAN |
| Final | 6/26/2023 | OK to Issue CofO | BRIAN SULLIVAN |