2693 W LOCKSLEY PL 90039
Certificate Information: 2693 W LOCKSLEY PL 90039
- Application / Permit
- 20014-10000-05169
- Plan Check / Job No.
- B20LA21665
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ONE STORY ADDITION TO (E) ONE STORY SINGLE FAMILY DWELLING & MAJOR REMODEL
- Permit Issued
- Issued on 7/22/2021
- Issuing Office
- Current Status
- CofO Issued on 9/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | GARO TELMI |
| Corrections Issued | 12/23/2020 | GARO TELMI |
| Quality Review Completed | 1/4/2021 | WING SUEN |
| Applicant returned to address corrections | 4/1/2021 | GARO TELMI |
| Plan Check Approved | 7/9/2021 | GARO TELMI |
| Plan Check Approved | 7/21/2021 | GARO TELMI |
| Issued | 7/22/2021 | APPLICANT |
| Building Plans Picked Up | 7/23/2021 | APPLICANT |
| CofO in Progress | 9/9/2022 | THOMAS LOGRASSO |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
| CofO Issued | 9/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 1/21/2021 | SARAHI ORTEGA |
| BHO/Hillside ordinance | Cleared | 1/27/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 1/27/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 1/27/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 1/27/2021 | WALLIE JONG |
| Address approval | Cleared | 2/11/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | WALLIE JONG |
| Sewer availability | Cleared | 2/16/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 2/25/2021 | JOHN CONNEALLY |
| Encroachment in public way | Cleared | 2/26/2021 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 3/19/2021 | THAN WIN |
| Highway dedication | Cleared | 3/19/2021 | THAN WIN |
| Low Impact Development | Cleared | 6/15/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/25/2021 | THAN WIN |
| GPI Written Notices | Cleared | 7/9/2021 | ROBERT HUGHES |
| Grading Pre-Inspection | Cleared | 7/9/2021 | ROBERT HUGHES |
Contact Information
| Architect | Neubert,, Aaron Douglas; Lic. No.: C29005 | 3052 BERKELEY CIRCLE LOS ANGELES, CA 90026 |
| Contractor | Owner-Builder | , |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/15/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/15/2021 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 10/15/2021 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/28/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 11/5/2021 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 11/5/2021 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2021 | Corrections Issued | THOMAS LOGRASSO |
| Wood Frame | 1/21/2022 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 1/25/2022 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Conditional Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/25/2022 | Approved | DANIEL GONZALEZ |
| HVAC-Rough | 2/25/2022 | Approved | DANIEL GONZALEZ |
| Interior/Exterior Lathing | 2/25/2022 | Partial Inspection | DANIEL GONZALEZ |
| Underground Mechanical | 2/25/2022 | Approved | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 2/28/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 2/28/2022 | Approved | THOMAS LOGRASSO |
| MERV13>=Rough | 2/28/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/28/2022 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 2/28/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 3/15/2022 | Conditional Approval | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 3/15/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 3/29/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 3/29/2022 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 4/4/2022 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/1/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 7/1/2022 | Corrections Issued | THOMAS LOGRASSO |
| Final | 7/1/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 7/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 7/1/2022 | Corrections Issued | THOMAS LOGRASSO |
| MERV13>=Final | 7/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 7/1/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 7/1/2022 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 7/1/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 7/7/2022 | Approved | THOMAS LOGRASSO |
| Final | 7/7/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 7/7/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 7/7/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 7/7/2022 | Approved | THOMAS LOGRASSO |
| Final | 7/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 7/18/2022 | Approved | THOMAS LOGRASSO |
| Final | 9/8/2022 | OK to Issue CofO | THOMAS LOGRASSO |