2333 S 6TH AVE 90018
Certificate Information: 2333 S 6TH AVE 90018
- Application / Permit
- 20014-10000-05137
- Plan Check / Job No.
- B20LA21585
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 1-CAR GARAGE TO ADU WITH A SECOND STORY ADDITION
- Permit Issued
- Issued on 3/29/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 1/15/2021 | CHUNG-WEN CHUANG |
| Quality Review Completed | 1/27/2021 | TIEN JEN WANG |
| Building Plans Picked Up | 1/28/2021 | APPLICANT |
| Applicant returned to address corrections | 11/7/2022 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 11/28/2022 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 5/23/2023 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 2/16/2024 | WEIJIAN HUANG |
| Applicant returned to address corrections | 3/4/2024 | WEIJIAN HUANG |
| Applicant returned to address corrections | 3/14/2024 | WEIJIAN HUANG |
| Applicant returned to address corrections | 3/28/2024 | WEIJIAN HUANG |
| Plan Check Approved | 3/29/2024 | WEIJIAN HUANG |
| Issued | 3/29/2024 | APPLICANT |
| CofO in Progress | 3/16/2026 | JUSTIN HAWLEY |
| Permit Finaled | 3/20/2026 | DEROLD HAUFF |
| CofO Issued | 3/20/2026 | DEROLD HAUFF |
| Permit Finaled | 3/20/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/23/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2021 | JEANIE LAM |
| CPC | Cleared | 6/3/2021 | ANACANY HURTADO |
| Hydrant and Access approval | Cleared | 7/19/2021 | MATTHEW CRAIG |
| HPOZ | Cleared | 1/17/2024 | DEBORAH MCGILL |
| Low Impact Development | Cleared | 1/26/2024 | PATRICK LOPEZ |
| ZI | Cleared | 2/14/2024 | DEBORAH MCGILL |
| Roof/Waste drainage to street | Cleared | 3/14/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Buzz - Ann Construction; Lic. No.: 777980-B | P O BOX 18661 LOS ANGELES, CA 900180661 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/10/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 4/22/2024 | Partial Approval | JUSTIN HAWLEY |
| Deputy Drilled-In Anchors | 4/24/2024 | Conditional Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 5/17/2024 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 5/17/2024 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 5/17/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/21/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 6/21/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Partial Approval | JUSTIN HAWLEY |
| Green Building Rough | 6/21/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| MERV13>=Rough | 6/21/2024 | Approved | JUSTIN HAWLEY |
| METHANE-Rough | 6/21/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Rough | 6/21/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 6/25/2024 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 6/25/2024 | Not Ready for Inspection | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2024 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Rough | 6/25/2024 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Rough | 6/25/2024 | Approved | JOSE MACIAS |
| METHANE-Rough | 6/25/2024 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Rough | 6/25/2024 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 6/28/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 6/28/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 6/28/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 7/5/2024 | Corrections Issued | JUSTIN HAWLEY |
| Insulation | 7/5/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 7/5/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Deputy Wood Construction | 7/8/2024 | Conditional Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 8/16/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 8/16/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 8/16/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/16/2024 | Partial Approval | JUSTIN HAWLEY |
| METHANE-Rough | 8/16/2024 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 8/30/2024 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 8/30/2024 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 11/26/2024 | Corrections Issued | JUSTIN HAWLEY |
| Service/Power Release | 11/26/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 1/13/2025 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 1/13/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| MERV13>=Final | 1/13/2025 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 1/13/2025 | SGSOV Not Required | JUSTIN HAWLEY |
| Smoke Detectors | 1/13/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Final | 2/10/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 2/10/2025 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 2/10/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Smoke Detectors | 2/10/2025 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 7/31/2025 | Approved | ARTHUR NEGRETE |
| Green Building Final | 7/31/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 7/31/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 7/31/2025 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 7/31/2025 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 11/13/2025 | Partial Inspection | ALEX COLIN |
| Special/Order Compliance | 11/14/2025 | Corrections Issued | ALEX COLIN |
| Final | 3/16/2026 | OK to Issue CofO | JUSTIN HAWLEY |