9000 N ODESSA AVE 91343

Certificate Information: 9000 N ODESSA AVE 91343

Application / Permit
20014-10000-05134
Plan Check / Job No.
B20LA21565
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Conversion of (E) rear covered patio into a living area and ground floor addition to the rear of (E) SFD.
Permit Issued
Issued on 3/16/2021
Issuing Office
Current Status
CofO Issued on 9/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2020 APPLICANT
Assigned to Plan Check Engineer 11/30/2020 HELEN NGUYEN
Corrections Issued 11/30/2020 HELEN NGUYEN
Applicant returned to address corrections 1/27/2021 HELEN NGUYEN
Applicant returned to address corrections 2/11/2021 LAMAR DAVIS
Plan Check Approved 3/4/2021 ZAW HAN
Issued 3/16/2021 APPLICANT
CofO in Progress 8/19/2022 RAUL OLAGI
Permit Finaled 9/3/2022 MICHAEL SMITH
CofO Issued 9/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/23/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/19/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/19/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/10/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 5/10/2021 Approved ARTHUR SARGSYAN
Wood Frame 6/18/2021 Partial Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 7/27/2021 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 7/27/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 7/27/2021 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 7/27/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 7/29/2021 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 7/29/2021 Approved DAVID SCANTLIN
Insulation 8/2/2021 Partial Inspection AMY COLIN
Drywall Nailing 9/10/2021 Approved JACK KARGODORIAN
Green Building Rough 9/10/2021 Approved JACK KARGODORIAN
Insulation 9/14/2021 Approved AMY COLIN
Interior/Exterior Lathing 9/14/2021 Approved AMY COLIN
BUILDING-Rough-Frame 5/11/2022 Approved RAUL OLAGI
ELECTRICAL-Final 5/11/2022 Approved RAUL OLAGI
Final 5/11/2022 Corrections Issued RAUL OLAGI
Green Building Final 5/11/2022 Approved RAUL OLAGI
HVAC-Final 5/11/2022 Approved RAUL OLAGI
PLUMBING-Final 5/11/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 5/11/2022 Approved RAUL OLAGI
Final 8/19/2022 OK to Issue CofO RAUL OLAGI
Reinforced Masonry Frame 8/19/2022 Approved RAUL OLAGI
Structural Steel Frame 8/19/2022 Approved RAUL OLAGI