4419 N BRUNSWICK AVE 90039

Certificate Information: 4419 N BRUNSWICK AVE 90039

Application / Permit
20014-10000-05107
Plan Check / Job No.
B20LA21498
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND 258 SQFT. ADDITION TO EXISTING 1-STORY SFD. NEW FRAMED DECK BETWEEN EXISTING RECREATION ROOM & SINGLE FAMILY DWELLING.
Permit Issued
Issued on 1/12/2021
Issuing Office
Current Status
CofO Issued on 9/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2020 APPLICANT
Assigned to Plan Check Engineer 12/4/2020 RICARDO RAMIREZ
Corrections Issued 12/5/2020 RICARDO RAMIREZ
Applicant returned to address corrections 1/5/2021 ZAW HAN
Plan Check Approved 1/7/2021 ZAW HAN
Issued 1/12/2021 APPLICANT
Building Plans Picked Up 1/14/2021 APPLICANT
CofO in Progress 5/12/2021 HAMIK HARTOUNIAN
Permit Finaled 9/11/2021 DEROLD HAUFF
CofO Issued 9/11/2021 DEROLD HAUFF
Permit Finaled 9/11/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/22/2020 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 12/23/2020 ROSA SILVA

Contact Information

Architect , ; Lic. No.: C38316       ,
Contractor Owner-Builder       ,
Engineer Rodriguez,, Jacob; Lic. No.: S5084 8206 ENCINO AVE      NORTHRIDGE, CA 91325

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/15/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/20/2021 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/20/2021 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 1/20/2021 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 1/20/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/26/2021 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/26/2021 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 1/26/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/26/2021 Partial Approval HAMIK HARTOUNIAN
Wood Frame 1/26/2021 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 1/29/2021 Approved HAMIK HARTOUNIAN
Insulation 1/29/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/29/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Shower Pan 1/29/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 1/29/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/2/2021 Partial Approval HAMIK HARTOUNIAN
Shower Pan 2/2/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 2/5/2021 Approved HAMIK HARTOUNIAN
Gas Test 2/5/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 2/5/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/5/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/11/2021 Approved HAMIK HARTOUNIAN
Final 5/11/2021 OK to Issue CofO HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/11/2021 Approved HAMIK HARTOUNIAN
Green Building Final 5/11/2021 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/11/2021 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 5/11/2021 Not Required HAMIK HARTOUNIAN
Smoke Detectors 5/11/2021 Approved HAMIK HARTOUNIAN