22117 W YBARRA ROAD 91364
Certificate Information: 22117 W YBARRA ROAD 91364
- Application / Permit
- 20014-10000-05104
- Plan Check / Job No.
- B20LA21449
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan ADDITION TO (E) SFD AND CONVERT (E) PATO TO LIVING AREA.
- Permit Issued
- Issued on 6/14/2021
- Issuing Office
- Current Status
- CofO Issued on 4/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 1/6/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 2/1/2021 | MINYE PAK |
| Applicant returned to address corrections | 5/17/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 6/2/2021 | CRYSTEL MAALOUF |
| Issued | 6/14/2021 | APPLICANT |
| CofO in Progress | 3/21/2022 | PETER FOLLING |
| Permit Finaled | 4/25/2023 | MICHAEL SMITH |
| CofO Issued | 4/25/2023 | MICHAEL SMITH |
| Permit Finaled | 4/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Specific Plan | Cleared | 2/10/2021 | LAURA FRAZIN-STEELE |
| ZI | Cleared | 2/10/2021 | LAURA FRAZIN-STEELE |
| Low Impact Development | Cleared | 5/5/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 5/6/2021 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2021 | ABDULLAH SADOZAI |
| GPI Written Notices | Cleared | 5/20/2021 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 5/20/2021 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Isaac,, Raymond; Lic. No.: NA84605 | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/21/2021 | Corrections Issued | PETER FOLLING |
| Footing/Foundation/Slab | 6/25/2021 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 7/27/2021 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 9/22/2021 | Corrections Issued | PETER FOLLING |
| Green Building Rough | 9/22/2021 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 10/1/2021 | Partial Approval | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2021 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 10/12/2021 | Corrections Issued | ROBERT GOLD |
| ELECTRICAL-Rough | 10/12/2021 | Not Ready for Inspection | ROBERT GOLD |
| Interior/Exterior Lathing | 10/12/2021 | Not Ready for Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/18/2021 | Partial Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 10/18/2021 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 10/18/2021 | Approved | ROBERT GOLD |
| HVAC-Rough | 10/22/2021 | No Access for Inspection | ROBERT GOLD |
| Insulation | 10/22/2021 | No Access for Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/25/2021 | Approved | PETER FOLLING |
| Green Building Rough | 10/25/2021 | Approved | PETER FOLLING |
| HVAC-Rough | 10/25/2021 | Approved | PETER FOLLING |
| Insulation | 10/25/2021 | Approved | PETER FOLLING |
| Drywall Nailing | 11/2/2021 | Approved | MORRIS JACKSON |
| Final | 1/20/2022 | Corrections Issued | PETER FOLLING |
| Green Building Final | 1/20/2022 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 1/20/2022 | Not Ready for Inspection | PETER FOLLING |
| Final | 1/26/2022 | Not Ready for Inspection | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 1/26/2022 | SGSOV Approved | PETER FOLLING |
| Smoke Detectors | 1/26/2022 | Not Ready for Inspection | PETER FOLLING |
| Final | 2/4/2022 | Not Ready for Inspection | PETER FOLLING |
| Final | 3/18/2022 | OK to Issue CofO | PETER FOLLING |
| Service/Power Release | 3/18/2022 | Approved | PETER FOLLING |
| Smoke Detectors | 3/18/2022 | Approved | PETER FOLLING |