16245 W MINNEHAHA ST 91344

Certificate Information: 16245 W MINNEHAHA ST 91344

Application / Permit
20014-10000-05093
Plan Check / Job No.
B20LA21338
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO AN EXISTING ONE STORY SFD WITH ATTACHED ADU
Permit Issued
Issued on 2/13/2021
Issuing Office
Current Status
CofO Issued on 6/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 TSE MING HUANG
Corrections Issued 12/13/2020 TSE MING HUANG
Applicant returned to address corrections 1/20/2021 RACHEL BEYENE
Plan Check Approved 1/27/2021 RAHEL BEYENE
Building Plans Picked Up 1/28/2021 APPLICANT
Issued 2/13/2021 APPLICANT
CofO in Progress 5/23/2022 MICHAEL TEMPLE
Permit Finaled 6/1/2022 MICHAEL SMITH
CofO Issued 6/1/2022 MICHAEL SMITH
Permit Finaled 6/1/2022 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 12/28/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/29/2020 GABRIEL ROBLES
Sewer availability Cleared 12/29/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 12/30/2020 GABRIEL ROBLES

Contact Information

Contractor Sarmiento Construction; Lic. No.: 819153-B 13012 WELBY WAY      NORTH HOLLYWOOD, CA 91606
Engineer Chan,, Albert Fong; Lic. No.: C61343 2261 PEPPERWOOD LN      CORONA, CA 92882

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/28/2021 Partial Inspection MARK JOHNSON
Deputy Drilled-In Anchors 8/12/2021 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 8/13/2021 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 9/8/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 9/13/2021 Partial Approval MARK JOHNSON
PLUMBING-Rough 9/13/2021 Partial Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 10/21/2021 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 11/22/2021 Approved MARK JOHNSON
PLUMBING-Rough 11/22/2021 Approved MARK JOHNSON
Wood Frame 11/22/2021 Not Ready for Inspection MARK JOHNSON
Deputy Wood Construction 11/23/2021 No Access for Inspection MARK JOHNSON
BUILDING-Rough-Frame 11/29/2021 Approved MARK JOHNSON
Green Building Rough 11/29/2021 Partial Approval MARK JOHNSON
Insulation 11/30/2021 Approved MARK JOHNSON
Drywall Nailing 12/2/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 12/7/2021 Approved JESUS RODRIGUEZ
Final 3/2/2022 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/2/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 3/2/2022 Approved JENNIFER RABUCHIN
Final 4/5/2022 Not Ready for Inspection JAVIER RAMOS JR
Final 5/2/2022 OK to Issue CofO JAVIER RAMOS JR