1138 W 68TH ST 90044
Certificate Information: 1138 W 68TH ST 90044
- Application / Permit
- 20014-10000-05034
- Plan Check / Job No.
- B20LA21140
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION (224 SF) + KITCHEN REMODELING & NEW [12X12] PATIO COVER.
- Permit Issued
- Issued on 3/30/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2020 | ZAW HAN |
| Corrections Issued | 12/8/2020 | ZAW HAN |
| Plan Check Approved | 2/24/2021 | JESSE JIMENEZ |
| Issued | 3/30/2021 | APPLICANT |
| Building Plans Picked Up | 4/1/2021 | APPLICANT |
| CofO in Progress | 2/14/2022 | FREDDIE RIVERA |
| Permit Finaled | 2/18/2023 | DANIEL ORRANTE |
| CofO Issued | 2/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 2/10/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 2/10/2021 | RENZ SORIANO |
Contact Information
| Contractor | J B New Construction Inc; Lic. No.: 923970-A | 13923 S CRENSHAW BLVD HAWTHORNE, CA 90250 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/19/2021 | Corrections Issued | FREDDIE RIVERA |
| Pre-Inspection | 4/19/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 4/28/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/10/2021 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2021 | Partial Approval | FREDDIE RIVERA |
| HVAC-Rough | 6/28/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 6/28/2021 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/20/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/20/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 7/20/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/20/2021 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/5/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/5/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 8/5/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 8/5/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Insulation | 8/5/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 8/5/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/16/2021 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/16/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 8/16/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 8/16/2021 | Approved | FREDDIE RIVERA |
| Insulation | 8/16/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 8/27/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/27/2021 | Corrections Issued | FREDDIE RIVERA |
| Service/Power Release | 9/24/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/31/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 1/31/2022 | Approved | FREDDIE RIVERA |
| Final | 1/31/2022 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/31/2022 | Approved | FREDDIE RIVERA |
| Green Building Final | 1/31/2022 | Approved | FREDDIE RIVERA |
| HVAC-Final | 1/31/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 1/31/2022 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 1/31/2022 | Approved | FREDDIE RIVERA |
| Final | 2/10/2022 | Conditional Approval | FREDDIE RIVERA |
| Final | 2/11/2022 | OK to Issue CofO | FREDDIE RIVERA |