24229 W PHILIPRIMM ST 91367
Certificate Information: 24229 W PHILIPRIMM ST 91367
- Application / Permit
- 20014-10000-05012
- Plan Check / Job No.
- B20LA21006
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (1-STORY) TO EXISTING SFD (1-STORY)
- Permit Issued
- Issued on 4/5/2021
- Issuing Office
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | CARLOS MONTES |
| Corrections Issued | 11/30/2020 | CARLOS MONTES |
| Quality Review Completed | 12/10/2020 | WING SUEN |
| Building Plans Picked Up | 1/12/2021 | APPLICANT |
| Applicant returned to address corrections | 1/27/2021 | CARLOS MONTES |
| Plan Check Approved | 3/22/2021 | CARLOS MONTES |
| Issued | 4/5/2021 | APPLICANT |
| CofO in Progress | 9/21/2023 | TROY SANDERS |
| Permit Finaled | 9/21/2023 | JOHN JANSON |
| CofO Issued | 9/21/2023 | JOHN JANSON |
| Permit Finaled | 9/21/2023 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/24/2020 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/15/2021 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 3/2/2021 | CARLOS MONTES |
| Low Impact Development | Cleared | 3/11/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/11/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/28/2021 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 4/30/2021 | No Access for Inspection | TROY SANDERS |
| Footing/Foundation/Slab | 5/18/2021 | Not Ready for Inspection | TROY SANDERS |
| Footing/Foundation/Slab | 5/27/2021 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 4/27/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 4/27/2022 | Approved | TROY SANDERS |
| Green Building Rough | 4/27/2022 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 4/27/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 4/27/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 6/15/2022 | Partial Approval | TROY SANDERS |
| Green Building Rough | 6/15/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 6/15/2022 | Partial Approval | TROY SANDERS |
| Shower Pan | 10/25/2022 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 12/9/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 3/29/2023 | Approved | TROY SANDERS |
| Pre-Inspection | 3/29/2023 | Partial Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 3/31/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 3/31/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 4/4/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 4/4/2023 | Partial Approval | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/4/2023 | SGSOV Not Ready | TROY SANDERS |
| ELECTRICAL-Final | 5/30/2023 | Approved | TROY SANDERS |
| Service/Power Release | 5/30/2023 | Approved | TROY SANDERS |
| Drywall Nailing | 6/7/2023 | Partial Approval | DAVID SCANTLIN |
| ELECTRICAL-Final | 6/7/2023 | Approved | DAVID SCANTLIN |
| Final | 6/7/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 6/7/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Final | 6/7/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 6/7/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 6/7/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 6/7/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Drywall Nailing | 8/14/2023 | Approved | TROY SANDERS |
| Final | 8/14/2023 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 8/14/2023 | Approved | TROY SANDERS |
| Smoke Detectors | 8/14/2023 | Approved | TROY SANDERS |
| Final | 9/21/2023 | OK to Issue CofO | TROY SANDERS |