1268 S MALCOLM AVE 90024

Certificate Information: 1268 S MALCOLM AVE 90024

Application / Permit
20014-10000-05001
Plan Check / Job No.
B20LA20964
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT WITH LOFT AND ATTACHED GARAGE. NEW TRELLIS AND ROOFTOP DECK ON TOP OF THE GARAGE.
Permit Issued
Issued on 4/28/2021
Issuing Office
Current Status
CofO Issued on 10/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2020 APPLICANT
Assigned to Plan Check Engineer 11/25/2020 FARSHAD ALIMOHAMADI
Corrections Issued 11/27/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 2/9/2021 GEORGE ALVAREZ
Plan Check Approved 4/27/2021 KEVIN MORALES
Issued 4/28/2021 APPLICANT
Building Plans Picked Up 6/3/2021 APPLICANT
CofO in Progress 10/4/2023 MICHAEL PELHAM
Permit Finaled 10/25/2023 DANIEL ORRANTE
CofO Issued 10/25/2023 DANIEL ORRANTE
Permit Finaled 10/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/9/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 12/14/2020 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 12/14/2020 BARTON HOLMES
Sewer availability Cleared 12/14/2020 ANTHONY MAINEZ
Construction near power lines Cleared 12/29/2020 RIDWAN HARDY
GPI Written Notices Cleared 2/16/2021 FARSHAD ALIMOHAMADI
Low Impact Development Cleared 4/1/2021 MARTIN FRAGOSO
Specific Plan Cleared 4/7/2021 EILEEN HUNT
Roof/Waste drainage to street Cleared 4/20/2021 JEANIE LAM

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Architect Strumwasser,, Scott Mark; Lic. No.: C21151 5971 W THIRD STREET      LOS ANGELES, CA 90036
Contractor Krumm Mike Construction Inc; Lic. No.: 915844-B 613 ONDA DRIVE      CAMARILLO, CA 93010
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/10/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 6/16/2021 Partial Approval KENNETH NAGLE
METHANE-Barrier 6/16/2021 Not Ready for Inspection KENNETH NAGLE
METHANE-Subgrade 6/16/2021 Not Ready for Inspection KENNETH NAGLE
Footing/Foundation/Slab 6/23/2021 Partial Approval OGANES TARAKHCHYAN
METHANE-Barrier 6/23/2021 Approved OGANES TARAKHCHYAN
METHANE-Subgrade 6/23/2021 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/2/2021 Corrections Issued OGANES TARAKHCHYAN
Green Building Rough 8/2/2021 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Rough 8/2/2021 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 8/2/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 8/10/2021 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/24/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/24/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 8/24/2021 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 8/24/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 8/24/2021 Approved OGANES TARAKHCHYAN
Verify Sprinkler Sign Off 8/24/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/10/2021 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 9/10/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/10/2021 Partial Approval OGANES TARAKHCHYAN
Insulation 9/21/2021 Approved OGANES TARAKHCHYAN
Drywall Nailing 9/24/2021 Approved JAVIER RAMOS JR
Shower Pan 9/30/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 10/4/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 10/19/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Service/Power Release 10/27/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 12/15/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 12/15/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 12/15/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Final 12/15/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 12/15/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/17/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 12/17/2021 Approved OGANES TARAKHCHYAN
Final 12/17/2021 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/17/2021 Approved OGANES TARAKHCHYAN
Green Building Final 12/17/2021 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 12/17/2021 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Final 12/17/2021 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/17/2021 SGSOV Not Required OGANES TARAKHCHYAN
Smoke Detectors 12/17/2021 Approved OGANES TARAKHCHYAN
Final 1/10/2022 Corrections Issued OGANES TARAKHCHYAN
Final 9/26/2023 Corrections Issued STEPHANIE SWANSON
Green Building Final 9/26/2023 Approved STEPHANIE SWANSON
Final 10/4/2023 OK to Issue CofO MICHAEL PELHAM