1268 S MALCOLM AVE 90024
Certificate Information: 1268 S MALCOLM AVE 90024
- Application / Permit
- 20014-10000-05001
- Plan Check / Job No.
- B20LA20964
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT WITH LOFT AND ATTACHED GARAGE. NEW TRELLIS AND ROOFTOP DECK ON TOP OF THE GARAGE.
- Permit Issued
- Issued on 4/28/2021
- Issuing Office
- Current Status
- CofO Issued on 10/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 11/27/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 2/9/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 4/27/2021 | KEVIN MORALES |
| Issued | 4/28/2021 | APPLICANT |
| Building Plans Picked Up | 6/3/2021 | APPLICANT |
| CofO in Progress | 10/4/2023 | MICHAEL PELHAM |
| Permit Finaled | 10/25/2023 | DANIEL ORRANTE |
| CofO Issued | 10/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2020 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 12/14/2020 | BARTON HOLMES |
| Sewer availability | Cleared | 12/14/2020 | ANTHONY MAINEZ |
| Construction near power lines | Cleared | 12/29/2020 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 2/16/2021 | FARSHAD ALIMOHAMADI |
| Low Impact Development | Cleared | 4/1/2021 | MARTIN FRAGOSO |
| Specific Plan | Cleared | 4/7/2021 | EILEEN HUNT |
| Roof/Waste drainage to street | Cleared | 4/20/2021 | JEANIE LAM |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Architect | Strumwasser,, Scott Mark; Lic. No.: C21151 | 5971 W THIRD STREET LOS ANGELES, CA 90036 |
| Contractor | Krumm Mike Construction Inc; Lic. No.: 915844-B | 613 ONDA DRIVE CAMARILLO, CA 93010 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/10/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/16/2021 | Partial Approval | KENNETH NAGLE |
| METHANE-Barrier | 6/16/2021 | Not Ready for Inspection | KENNETH NAGLE |
| METHANE-Subgrade | 6/16/2021 | Not Ready for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 6/23/2021 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Barrier | 6/23/2021 | Approved | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 6/23/2021 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/2/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Rough | 8/2/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Rough | 8/2/2021 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 8/2/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/10/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/24/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/24/2021 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 8/24/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 8/24/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/24/2021 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 8/24/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/10/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 9/10/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/10/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 9/21/2021 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 9/24/2021 | Approved | JAVIER RAMOS JR |
| Shower Pan | 9/30/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/4/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/19/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Service/Power Release | 10/27/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 12/15/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/15/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 12/15/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 12/15/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/15/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/17/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 12/17/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 12/17/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/17/2021 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 12/17/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 12/17/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Final | 12/17/2021 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/17/2021 | SGSOV Not Required | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/17/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 1/10/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 9/26/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 9/26/2023 | Approved | STEPHANIE SWANSON |
| Final | 10/4/2023 | OK to Issue CofO | MICHAEL PELHAM |