1333 W F ST 90744
Certificate Information: 1333 W F ST 90744
- Application / Permit
- 20014-10000-04973
- Plan Check / Job No.
- B20LA20899
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- e-plan:CONVERT EXISTING DETACHED GARAGE TO 2- STORY ATTACHED ACCESSORY DWELLING UNIT W/ PROPOSED PATIO COVER
- Permit Issued
- Issued on 10/15/2021
- Issuing Office
- Current Status
- CofO Issued on 5/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 12/15/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 12/29/2020 | WING SUEN |
| Applicant returned to address corrections | 5/7/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 6/16/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 7/21/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 8/19/2021 | CRYSTEL MAALOUF |
| Issued | 10/15/2021 | APPLICANT |
| CofO in Progress | 5/4/2023 | EUGENE CASSIDY |
| Permit Finaled | 5/9/2023 | DANIEL ORRANTE |
| CofO Issued | 5/9/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/9/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 2/11/2021 | KENTON TRINH |
| Address approval | Cleared | 3/10/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2021 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/22/2021 | ERIK BEASLEY |
| Construction near power lines | Cleared | 4/5/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/18/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/20/2021 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Movahedpour,, Mohsen Max; Lic. No.: C60892 | 41319 12TH ST WEST 103 PALMDALE, CA 93551 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/24/2022 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 2/24/2022 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/24/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Barrier | 2/24/2022 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 2/24/2022 | Approved | EUGENE CASSIDY |
| Deputy Wood Construction | 8/10/2022 | Partial Approval | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 8/23/2022 | Partial Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 9/1/2022 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/31/2023 | Approved | EUGENE CASSIDY |
| Final | 3/31/2023 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/31/2023 | Approved | EUGENE CASSIDY |
| Green Building Final | 3/31/2023 | Approved | EUGENE CASSIDY |
| Green Building Rough | 3/31/2023 | Approved | EUGENE CASSIDY |
| MERV13>=Final | 3/31/2023 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 3/31/2023 | Approved | EUGENE CASSIDY |
| METHANE-Final | 3/31/2023 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 3/31/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 3/31/2023 | Approved | EUGENE CASSIDY |
| Final | 4/7/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/3/2023 | Approved | EUGENE CASSIDY |
| Final | 5/3/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 5/3/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 5/3/2023 | Approved | EUGENE CASSIDY |