16306 S DENVER AVE 90248

Certificate Information: 16306 S DENVER AVE 90248

Application / Permit
20014-10000-04961
Plan Check / Job No.
B20LA20833
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING SFD 1-STORY AND REMOVE ATTACHED 1-CAR GARAGE
Permit Issued
Issued on 10/17/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 CARLOS MONTES
Corrections Issued 1/13/2021 CARLOS MONTES
Quality Review Completed 1/13/2021 TU HUA
Building Plans Picked Up 1/19/2021 APPLICANT
Applicant returned to address corrections 3/12/2021 CARLOS MONTES
Plan Check Approved 10/17/2022 CARLOS MONTES
Issued 10/17/2022 APPLICANT
CofO in Progress 11/20/2023 JAMES CHAVEZ
Permit Finaled 11/20/2023 ANSON MAGLASANG
CofO Issued 11/20/2023 ANSON MAGLASANG
Permit Finaled 11/20/2023 ANSON MAGLASANG

Permit Application Clearance Information

Sewer availability Cleared 5/12/2021 CHINH DINH
Low Impact Development Cleared 9/1/2022 CHRIS VONG
Eng Process Fee Ord 176,300 Cleared 9/15/2022 HUGO LOPEZ
Roof/Waste drainage to street Cleared 9/15/2022 HUGO LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Vo,, Tung Thanh; Lic. No.: C69546 9756 EMMONS CIR      FOUNTAIN VALLEY, CA 92708

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/19/2022 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 1/6/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Corrections Issued JAMES CHAVEZ
Green Building Rough 1/19/2023 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Rough 1/19/2023 Not Ready for Inspection JAMES CHAVEZ
Underground Mechanical 1/19/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Not Ready for Inspection JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 2/9/2023 Partial Inspection JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 2/13/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 2/28/2023 Conditional Approval JAMES CHAVEZ
ELECTRICAL-Rough 2/28/2023 Approved JAMES CHAVEZ
Green Building Rough 2/28/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 2/28/2023 Approved JAMES CHAVEZ
MERV13>=Rough 2/28/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 2/28/2023 Approved JAMES CHAVEZ
Green Building Rough 3/16/2023 Approved JAMES CHAVEZ
Shower Pan 3/16/2023 Approved JAMES CHAVEZ
Insulation 3/20/2023 Approved JAMES CHAVEZ
Drywall Nailing 3/28/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 3/28/2023 Partial Approval JAMES CHAVEZ
Interior/Exterior Lathing 4/27/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 9/28/2023 Approved JAMES CHAVEZ
Final 9/28/2023 Corrections Issued JAMES CHAVEZ
Gas Test 9/28/2023 Approved JAMES CHAVEZ
Green Building Final 9/28/2023 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Final 9/28/2023 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 9/28/2023 Not Ready for Inspection JAMES CHAVEZ
Final 11/3/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 11/3/2023 Approved JAMES CHAVEZ
MERV13>=Final 11/3/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 11/3/2023 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 11/3/2023 Approved JAMES CHAVEZ
Final 11/20/2023 OK to Issue CofO JAMES CHAVEZ