3433 E MERCED ST 90065

Certificate Information: 3433 E MERCED ST 90065

Application / Permit
20014-10000-04920
Plan Check / Job No.
B20LA20704
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF (E) GARAGE TO ADU W/ ROOF DECK PER GCS 65852.2 & 65852.22
Permit Issued
Issued on 3/15/2021
Issuing Office
Current Status
CofO Issued on 9/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2020 APPLICANT
Assigned to Plan Check Engineer 12/10/2020 HERNAN ARREOLA
Corrections Issued 12/14/2020 HERNAN ARREOLA
Quality Review Completed 12/21/2020 ALLEN MANALANSAN
Building Plans Picked Up 12/22/2020 APPLICANT
Plan Check Approved 3/13/2021 HERNAN ARREOLA
Issued 3/15/2021 APPLICANT
CofO in Progress 9/3/2022 OSVALDO PARAMO
CofO in Progress 9/3/2022 OSVALDO PARAMO
Permit Finaled 9/11/2022 DEROLD HAUFF
CofO Issued 9/11/2022 DEROLD HAUFF
Permit Finaled 9/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/20/2021 MATTHEW CRAIG
Supp. Use District POD/CDO/TDO Cleared 1/20/2021 ADRINEH MELKONIAN
ZI Cleared 1/20/2021 ADRINEH MELKONIAN
Address approval Cleared 2/16/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 2/16/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/17/2021 JEANIE LAM
Sewer availability Cleared 2/17/2021 JEANIE LAM
Grading Pre-Inspection Cleared 3/13/2021 HERNAN ARREOLA

Contact Information

Contractor Owner-Builder       ,
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/4/2021 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 8/13/2021 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 8/13/2021 Not Ready for Inspection OSVALDO PARAMO
Underground Mechanical 8/13/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 8/17/2021 Approved OSVALDO PARAMO
Footing/Foundation/Slab 8/17/2021 Approved OSVALDO PARAMO
Piling/Pier/Caisson 8/17/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/20/2021 Partial Approval OSVALDO PARAMO
Deputy Steel/Welding 9/15/2021 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 9/30/2021 Approved OSVALDO PARAMO
HVAC-Rough 9/30/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 9/30/2021 Approved OSVALDO PARAMO
Deck 10/1/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Approved OSVALDO PARAMO
Wood Frame 10/1/2021 Approved OSVALDO PARAMO
Green Building Rough 10/18/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/18/2021 Partial Approval OSVALDO PARAMO
Insulation 12/7/2021 Not Ready for Inspection OSVALDO PARAMO
Insulation 12/13/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 12/13/2021 Approved OSVALDO PARAMO
Drywall Nailing 12/28/2021 Not Ready for Inspection JOSEPH MCGARRY
Drywall Nailing 12/30/2021 Corrections Issued HAMIK HARTOUNIAN
Drywall Nailing 1/10/2022 Approved OSVALDO PARAMO
Shower Pan 2/16/2022 Approved OSVALDO PARAMO
Special/Order Compliance 2/16/2022 Partial Inspection ALIZAH MAYAGOITIA
Sewer 3/14/2022 Approved OSVALDO PARAMO
Underground Mechanical 3/14/2022 Approved OSVALDO PARAMO
ELECTRICAL-Final 4/8/2022 Partial Inspection SCOTT FINNILA
HVAC-Final 4/8/2022 Partial Inspection SCOTT FINNILA
Smoke Detectors 4/8/2022 Approved SCOTT FINNILA
Interior/Exterior Lathing 4/13/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 8/11/2022 Approved OSVALDO PARAMO
Final 8/11/2022 Corrections Issued OSVALDO PARAMO
Green Building Final 8/11/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Approved OSVALDO PARAMO
Final 8/31/2022 OK to Issue CofO OSVALDO PARAMO