723 E BROOKS AVE 90291
Certificate Information: 723 E BROOKS AVE 90291
- Application / Permit
- 20014-10000-04858
- Plan Check / Job No.
- B20LA20471
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2ND STORY ACCESSORY DWELLING UNIT ADDITION TO (E) 1-CAR GARAGE PER LAMC 12.22.A.33
- Permit Issued
- Issued on 9/29/2021
- Issuing Office
- Current Status
- CofO Issued on 9/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | DANIEL YIP |
| Corrections Issued | 12/30/2020 | DANIEL YIP |
| Quality Review Completed | 1/4/2021 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 6/10/2021 | DANIEL YIP |
| Applicant returned to address corrections | 8/19/2021 | DANIEL YIP |
| Plan Check Approved | 9/7/2021 | DANIEL YIP |
| Issued | 9/29/2021 | APPLICANT |
| Building Plans Picked Up | 10/1/2021 | APPLICANT |
| CofO in Progress | 9/5/2024 | HERBERT GIRON |
| Permit Finaled | 9/7/2024 | RICHARD STEINBACH |
| CofO Issued | 9/7/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/7/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 2/10/2021 | SAUL GARCIA |
| Low Impact Development | Cleared | 7/8/2021 | JORGE MEJIA LEMUS |
| Coastal Zone | Cleared | 7/28/2021 | NOAH MCCOY |
| Miscellaneous | Cleared | 7/28/2021 | NOAH MCCOY |
| Specific Plan | Cleared | 7/28/2021 | NOAH MCCOY |
| ZA Case | Cleared | 7/28/2021 | NOAH MCCOY |
| Roof/Waste drainage to street | Cleared | 8/3/2021 | SAUL GARCIA |
| Specific Plan | Cleared | 8/23/2021 | VALERIA CEJA |
Contact Information
| Architect | Bambrough,, Patrick; Lic. No.: C34299 | 4132 ALLA ROAD LOS ANGELES, CA 90066 |
| Architect | Thibodeau,, Robert E; Lic. No.: C25585 | 812 LINCOLN BLVD VENICE, CA 90291 |
| Contractor | Termini Mark; Lic. No.: 779890-B | 22365 PRAIRE RD LAKE FOREST, CA 92630 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/26/2021 | Partial Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 1/14/2022 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 1/24/2022 | Approved | DAVID FEILER |
| PLUMBING-Rough | 1/24/2022 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Partial Approval | STEPHANIE SWANSON |
| Underground Mechanical | 7/11/2022 | Corrections Issued | DAVID FEILER |
| Underground Mechanical | 7/14/2022 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 7/25/2022 | Partial Approval | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 12/19/2022 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 12/21/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 12/22/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 1/13/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2023 | Partial Approval | EVAN COOPER |
| Green Building Rough | 1/13/2023 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 1/13/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/13/2023 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 1/27/2023 | Approved | EVAN COOPER |
| Green Building Rough | 1/27/2023 | Approved | EVAN COOPER |
| Insulation | 1/27/2023 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 1/27/2023 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 2/21/2023 | Partial Approval | EVAN COOPER |
| Insulation | 3/21/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/23/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 4/4/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/4/2023 | Approved | HERBERT GIRON |
| Shower Pan | 4/4/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 8/22/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 9/8/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 9/25/2023 | Approved | HERBERT GIRON |
| Service/Power Release | 9/25/2023 | Approved | HERBERT GIRON |
| Service/Power Release | 9/29/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 12/7/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 3/7/2024 | Corrections Issued | HERBERT GIRON |
| Final | 5/24/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 5/24/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 5/24/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 5/24/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 5/24/2024 | SGSOV Not Required | HERBERT GIRON |
| Smoke Detectors | 5/24/2024 | Approved | HERBERT GIRON |
| Final | 9/4/2024 | OK to Issue CofO | HERBERT GIRON |
| Green Building Final | 9/4/2024 | Approved | HERBERT GIRON |
| HVAC-Final | 9/4/2024 | Approved | HERBERT GIRON |