1625 N AVENUE 45 90041
Certificate Information: 1625 N AVENUE 45 90041
- Application / Permit
- 20014-10000-04847
- Plan Check / Job No.
- B20LA20427
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One-story, ground floor addition and exterior alteration to an (E) single family dwelling to extend (E) dining room (52 SF), create attached trellis (38 SF), and modify (E) building facade. All work per engineered design.
- Permit Issued
- Issued on 4/7/2021
- Issuing Office
- Current Status
- CofO Issued on 9/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2020 | CHRISTOPHER KOMANCHECK |
| Corrections Issued | 11/19/2020 | CHRISTOPHER KOMANCHECK |
| Applicant returned to address corrections | 3/3/2021 | LUKE GONZALES |
| Plan Check Approved | 3/31/2021 | SAMUEL GONZALEZ |
| Issued | 4/7/2021 | APPLICANT |
| Building Plans Picked Up | 4/9/2021 | APPLICANT |
| CofO in Progress | 9/13/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 9/24/2021 | DEROLD HAUFF |
| CofO Issued | 9/24/2021 | DEROLD HAUFF |
| Permit Finaled | 9/24/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 2/9/2021 | MIGUEL GAMBOA |
| Roof/Waste drainage to street | Cleared | 2/9/2021 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 2/17/2021 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rivera,, Bobby Zulueta; Lic. No.: C77218 | 14703 HELWIG AVE NORWALK, CA 90650 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/18/2021 | Partial Inspection | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 5/26/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 5/27/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/3/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/10/2021 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 6/10/2021 | Approved | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 6/11/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/22/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/22/2021 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/15/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2021 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/21/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Insulation | 7/21/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/21/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 7/23/2021 | Corrections Issued | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 7/23/2021 | Approved | JUSTIN HAWLEY |
| Insulation | 7/27/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Insulation | 8/4/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 8/13/2021 | No Access for Inspection | BRAD BESCOS |
| BUILDING-Rough-Frame | 8/16/2021 | Not Ready for Inspection | COREY HUPP |
| Drywall Nailing | 8/16/2021 | Approved | COREY HUPP |
| Final | 9/2/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 9/2/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/2/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/10/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 9/10/2021 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/10/2021 | Approved | HAMIK HARTOUNIAN |