14328 W ADDISON ST 91423

Certificate Information: 14328 W ADDISON ST 91423

Application / Permit
20014-10000-04841
Plan Check / Job No.
B20LA20380
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Remodel unit #9 in an (E) 9-unit apartment.
Permit Issued
Issued on 4/8/2021
Issuing Office
Current Status
Permit Finaled on 8/9/2021

Permit Application Status History

Submitted 11/10/2020 APPLICANT
Assigned to Plan Check Engineer 11/20/2020 HELEN NGUYEN
Corrections Issued 11/23/2020 HELEN NGUYEN
Quality Review Completed 11/25/2020 TU HUA
Building Plans Picked Up 11/30/2020 APPLICANT
Disabled Access Plans Picked Up 12/7/2020 APPLICANT
Applicant returned to address corrections 2/8/2021 HELEN NGUYEN
Green Plans Picked Up 3/18/2021 APPLICANT
Applicant returned to address corrections 3/25/2021 HELEN NGUYEN
Applicant returned to address corrections 4/6/2021 HELEN NGUYEN
Plan Check Approved 4/7/2021 HELEN NGUYEN
Issued 4/8/2021 APPLICANT
Permit Finaled 8/9/2021 CAMERON CHABAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/8/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 12/8/2020 JEANIE LAM
DAS Clearance Cleared 1/11/2021 SHINE LIN
Tenant Habitability Plan Cleared 1/25/2021 MICHAEL SOTO
Low Impact Development Cleared 3/1/2021 ANDRES COVARRUBIAS
Hydrant and Access approval Cleared 3/2/2021 MATTHEW CRAIG
Green Code Cleared 3/17/2021 HELEN NGUYEN

Contact Information

Contractor 1st Choice Development; Lic. No.: 576474-B 2400 E KATELLA AVENUE #800      ANAHEIM, CA 92806
Engineer Truong,, Phong Lap; Lic. No.: C70784 20754 TIMBERLINE LN      WALNUT, CA 91789

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 4/12/2021 Not Ready for Inspection CAMERON CHABAN
Wood Frame 4/12/2021 Not Ready for Inspection CAMERON CHABAN
Green Building Rough 4/16/2021 Not Ready for Inspection CAMERON CHABAN
Wood Frame 4/16/2021 Corrections Issued CAMERON CHABAN
Green Building Rough 4/29/2021 Approved CAMERON CHABAN
Insulation 4/29/2021 Approved CAMERON CHABAN
Wood Frame 4/29/2021 Approved CAMERON CHABAN
Drywall Nailing 5/5/2021 Approved CAMERON CHABAN
Special/Order Compliance 5/5/2021 Not Ready for Inspection CAMERON CHABAN
Final 7/26/2021 Not Ready for Inspection CAMERON CHABAN
Footing/Foundation/Slab 7/26/2021 Partial Inspection CAMERON CHABAN
Green Building Final 7/26/2021 Not Ready for Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 7/26/2021 SGSOV Not Ready CAMERON CHABAN
Smoke Detectors 7/26/2021 Not Ready for Inspection CAMERON CHABAN
Green Building Final 7/29/2021 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 7/30/2021 SGSOV Not Ready CAMERON CHABAN
Final 8/9/2021 Permit Finaled CAMERON CHABAN
Footing/Foundation/Slab 8/9/2021 Approved CAMERON CHABAN
Green Building Final 8/9/2021 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 8/9/2021 SGSOV Approved CAMERON CHABAN
Smoke Detectors 8/9/2021 Approved CAMERON CHABAN