4249 W NEWDALE DR 90027
Certificate Information: 4249 W NEWDALE DR 90027
- Application / Permit
- 20014-10000-04839
- Plan Check / Job No.
- B20LA20378
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ADDITION TO (E) DUPLEX AND EXTERIOR REMODEL. ADDITION TO UNIT #1
- Permit Issued
- Issued on 1/5/2021
- Issuing Office
- Current Status
- CofO Issued on 12/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 11/14/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 11/18/2020 | TIEN JEN WANG |
| Building Plans Picked Up | 11/19/2020 | APPLICANT |
| Plan Check Approved | 12/31/2020 | MAHNAZ NOURHASHEMI |
| Issued | 1/5/2021 | APPLICANT |
| CofO in Progress | 3/11/2022 | JOSEPH MCGARRY |
| Permit Finaled | 12/31/2022 | DEROLD HAUFF |
| CofO Issued | 12/31/2022 | DEROLD HAUFF |
| Permit Finaled | 12/31/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/23/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/23/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/23/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/23/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 11/23/2020 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 11/23/2020 | CELINA MORENO |
| Tenant Habitability Plan | Cleared | 11/24/2020 | MICHAEL GREGERSON |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 12/31/2020 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Simonian,, Ara; Lic. No.: C37208 | 314 E BROADWAY STE A GLENDALE, CA 91205 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/15/2021 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 1/15/2021 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 2/4/2021 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 2/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 2/17/2021 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/1/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 3/1/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 3/1/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/15/2021 | Conditional Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 3/15/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/15/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 3/15/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 3/15/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/15/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/23/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/23/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 3/24/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 4/5/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/4/2021 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 5/4/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 5/4/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 5/4/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 5/4/2021 | Approved | JOSEPH MCGARRY |
| Final | 8/6/2021 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/6/2021 | Approved | JOSEPH MCGARRY |
| Green Building Final | 8/6/2021 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 8/6/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 8/6/2021 | Approved | JOSEPH MCGARRY |
| Final | 10/19/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 3/8/2022 | Approved | JOSEPH MCGARRY |
| Final | 3/8/2022 | OK to Issue CofO | JOSEPH MCGARRY |
| HVAC-Final | 3/8/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 3/8/2022 | Approved | JOSEPH MCGARRY |