260 S LORRAINE BLVD 90004

Certificate Information: 260 S LORRAINE BLVD 90004

Application / Permit
20014-10000-04838
Plan Check / Job No.
B20LA20369
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO (E) SFD.
Permit Issued
Issued on 4/9/2021
Issuing Office
Current Status
Issued on 4/9/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/3/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 CRYSTEL MAALOUF
Corrections Issued 12/14/2020 CRYSTEL MAALOUF
Quality Review Completed 12/28/2020 WING SUEN
Applicant returned to address corrections 3/3/2021 CRYSTEL MAALOUF
Plan Check Approved 4/9/2021 CRYSTEL MAALOUF
Issued 4/9/2021 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/25/2021 WALLIE JONG
Sewer availability Cleared 1/25/2021 WALLIE JONG
CPC Cleared 2/2/2021 CHRISTINA PARK
CPC Cleared 2/2/2021 CHRISTINA PARK
CPC Cleared 2/2/2021 CHRISTINA PARK
HPOZ Cleared 2/2/2021 CHRISTINA PARK
Eng Process Fee Ord 176,300 Cleared 4/6/2021 PAMELA TENEZA
Miscellaneous Cleared 4/6/2021 TERRI OSBORNE

Contact Information

Contractor Hartman Baldwin Inc; Lic. No.: 653340-B 100 WEST FOOTHILL BLVD      CLAREMONT, CA 91711
Engineer Mutka,, Jason Richard; Lic. No.: C72255 PO BOX 77144      CORONA, CA 92877

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/3/2021 Conditional Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/11/2021 Approved CHRIS CHRISTENSEN
Gas Test 6/11/2021 Approved CHRIS CHRISTENSEN
Sewer 6/11/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/15/2021 Approved CHRIS CHRISTENSEN
Gas Test 6/15/2021 Approved CHRIS CHRISTENSEN
Sewer 6/15/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/8/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/8/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 9/8/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 9/8/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 9/8/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/22/2021 Partial Approval JOSEPH MCGARRY
Insulation 9/22/2021 Conditional Approval JOSEPH MCGARRY
Drywall Nailing 10/8/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 12/15/2021 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 12/21/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/11/2022 Partial Approval JEFFREY MEAD
Final 8/11/2022 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 8/11/2022 Approved JEFFREY MEAD
Green Building Final 8/11/2022 Partial Approval JEFFREY MEAD
Green Building Rough 8/11/2022 Not Ready for Inspection JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Approved JEFFREY MEAD
Smoke Detectors 8/11/2022 Corrections Issued JEFFREY MEAD