7027 N CLAIRE AVE 91335
Certificate Information: 7027 N CLAIRE AVE 91335
- Application / Permit
- 20014-10000-04817
- Plan Check / Job No.
- B20LA20289
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached garage to adu and add 407 sq.ft.
- Permit Issued
- Issued on 6/22/2021
- Issuing Office
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 12/2/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 12/22/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 5/13/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 6/17/2021 | ARSALAN SHABESTARI |
| Issued | 6/22/2021 | APPLICANT |
| CofO in Progress | 4/13/2023 | VINCENT HANLEY |
| Permit Finaled | 4/18/2023 | JOHN JANSON |
| CofO Issued | 4/18/2023 | JOHN JANSON |
| Permit Finaled | 4/18/2023 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/17/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/17/2021 | RIDWAN HARDY |
| Address approval | Cleared | 4/14/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 4/14/2021 | JOHN TRIANTAFYLLOS |
| ZI | Cleared | 4/15/2021 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/19/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/1/2022 | Partial Approval | VINCENT HANLEY |
| Sewer | 2/1/2022 | Approved | VINCENT HANLEY |
| Underground Mechanical | 2/1/2022 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 2/14/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/14/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/16/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/16/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2022 | Partial Approval | VINCENT HANLEY |
| HVAC-Rough | 3/16/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 3/16/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/21/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 3/21/2022 | Approved | VINCENT HANLEY |
| Insulation | 3/21/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/21/2022 | Approved | VINCENT HANLEY |
| Shower Pan | 3/21/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 3/24/2022 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 4/27/2022 | Corrections Issued | VINCENT HANLEY |
| Final | 4/27/2022 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 4/27/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/27/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/27/2022 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 4/27/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/3/2022 | Approved | VINCENT HANLEY |
| Final | 5/3/2022 | Corrections Issued | VINCENT HANLEY |
| Final | 4/13/2023 | OK to Issue CofO | VINCENT HANLEY |