8037 S WESTLAWN AVE 90045

Certificate Information: 8037 S WESTLAWN AVE 90045

Application / Permit
20014-10000-04782
Plan Check / Job No.
B20LA20156
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ADDITIONS TO DETACHED GARAGE OF A NEW RECREATION ROOM, 130 SQ FT STORAGE ROOM, AND 190 SQ FT. COVERED PATIO. GARAGE ROOF FRAMING TO BE REPLACED.
Permit Issued
Issued on 5/11/2021
Issuing Office
Current Status
CofO Issued on 3/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/13/2020 FERNANDO FLORES
Corrections Issued 11/14/2020 FERNANDO FLORES
Applicant returned to address corrections 1/6/2021 ADAM HEGAZI
Applicant returned to address corrections 4/13/2021 SINA KHOSRAVI
Plan Check Approved 5/7/2021 LUKE GONZALES
Plan Check Approved 5/11/2021 LUKE GONZALES
Issued 5/11/2021 APPLICANT
Building Plans Picked Up 5/13/2021 APPLICANT
CofO in Progress 12/15/2021 DAVID FEILER
Permit Finaled 3/16/2022 DANIEL ORRANTE
CofO Issued 3/16/2022 DANIEL ORRANTE
Permit Finaled 3/16/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 12/10/2020 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 12/30/2020 JUAN ASHTON
Sewer availability Cleared 1/25/2021 ANTHONY MAINEZ
Construction near power lines Cleared 3/20/2021 RIDWAN HARDY
Low Impact Development Cleared 3/29/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/6/2021 JUAN ASHTON

Contact Information

Contractor Custom Design & Construction; Lic. No.: 524561-B 2001 E MARIPOSA AVE      EL SEGUNDO, CA 90245
Engineer Bustillos, Portillo, Alejandro Ivan; Lic. No.: C87257 4749 W 169TH STREET      LAWNDALE, CA 90260

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/29/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 6/29/2021 Approved BRENDAN LOONEY
ELECTRICAL-Rough 7/6/2021 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 7/6/2021 Conditional Approval BRENDAN LOONEY
BUILDING-Rough-Frame 8/11/2021 Conditional Approval BRENDAN LOONEY
ELECTRICAL-Rough 8/11/2021 Approved BRENDAN LOONEY
Green Building Rough 8/11/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 8/11/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 8/18/2021 Approved BRENDAN LOONEY
Green Building Rough 8/18/2021 Approved BRENDAN LOONEY
Insulation 8/18/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 8/18/2021 Partial Approval BRENDAN LOONEY
Drywall Nailing 8/23/2021 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 8/23/2021 Approved SHAVONNE ESPINOZA
PLUMBING-Rough 9/27/2021 Partial Inspection BRENDAN LOONEY
ELECTRICAL-Final 11/17/2021 Approved ENRIQUE MIRELES
Final 11/17/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 11/17/2021 Approved ENRIQUE MIRELES
Green Building Final 11/17/2021 Approved ENRIQUE MIRELES
HVAC-Final 11/17/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 11/17/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 11/17/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 11/17/2021 Approved ENRIQUE MIRELES
Final 12/14/2021 OK to Issue CofO DAVID FEILER