10431 W NORTHVALE ROAD 90064

Certificate Information: 10431 W NORTHVALE ROAD 90064

Application / Permit
20014-10000-04781
Plan Check / Job No.
B20LA20145
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD BEDROOM RESTROOM WITHIN EXISTING LIVING SPACE. ADD WALK IN CLOSET.
Permit Issued
Issued on 4/9/2021
Issuing Office
Current Status
Issued on 5/2/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/9/2020 CRISTINA SALAZAR
Corrections Issued 11/9/2020 CRISTINA SALAZAR
Applicant returned to address corrections 2/3/2021 SAMUEL GONZALEZ
Plan Check Approved 3/1/2021 ADAM HEGAZI
Issued 4/9/2021 APPLICANT
Building Plans Picked Up 4/14/2021 APPLICANT
CofO in Progress 12/3/2021 KEVIN SARGSYAN
No Progress 5/2/2022 KENNETH NAGLE

Permit Application Clearance Information

Specific Plan Cleared 11/13/2020 DYLAN SITTIG
Eng Process Fee Ord 176,300 Cleared 12/23/2020 TRACY TATE
Roof/Waste drainage to street Cleared 1/5/2021 TRACY TATE
Sewer availability Cleared 1/5/2021 TRACY TATE
Specific Plan Cleared 1/20/2021 DYLAN SITTIG
Grading Pre-Inspection Cleared 2/3/2021 CRISTINA SALAZAR
Specific Plan Cleared 2/16/2021 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/2/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 7/15/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 8/10/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 8/10/2021 Approved EVAN COOPER
Green Building Rough 8/10/2021 Not Ready for Inspection EVAN COOPER
MERV13>=Rough 8/10/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 8/10/2021 Partial Approval EVAN COOPER
Interior/Exterior Lathing 8/26/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 8/26/2021 Corrections Issued KEVIN SARGSYAN
Shower Pan 8/26/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 8/30/2021 Approved KEVIN SARGSYAN
Green Building Rough 8/30/2021 Approved KEVIN SARGSYAN
Insulation 8/30/2021 Approved KEVIN SARGSYAN
MERV13>=Rough 8/30/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 8/30/2021 Approved KEVIN SARGSYAN
Drywall Nailing 9/13/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/13/2021 Approved KEVIN SARGSYAN
Final 11/12/2021 Corrections Issued KEVIN SARGSYAN
Green Building Final 11/12/2021 Approved KEVIN SARGSYAN
MERV13>=Final 11/12/2021 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/12/2021 SGSOV Approved KEVIN SARGSYAN
Shower Pan 11/12/2021 Approved KEVIN SARGSYAN
Smoke Detectors 11/12/2021 Approved KEVIN SARGSYAN
Final 11/22/2021 Corrections Issued KEVIN SARGSYAN
Final 12/3/2021 OK to Issue CofO KEVIN SARGSYAN