6111 E MERIDIAN ST 90042
Certificate Information: 6111 E MERIDIAN ST 90042
- Application / Permit
- 20014-10000-04780
- Plan Check / Job No.
- B20LA20129
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND NEW ADDITION TO (E) SINGLE FAMILY DWELLING. NEW ROOF FRAMING. NFPA-13D FIRE SPRINKLERS REQUIRED.
- Permit Issued
- Issued on 6/10/2021
- Issuing Office
- Current Status
- CofO Issued on 8/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2020 | KEVIN MORALES |
| Corrections Issued | 12/23/2020 | KEVIN MORALES |
| Quality Review Completed | 12/28/2020 | EUGENE BARBEAU |
| Plan Check Approved | 5/25/2021 | KEVIN MORALES |
| Issued | 6/10/2021 | APPLICANT |
| Building Plans Picked Up | 6/18/2021 | APPLICANT |
| CofO in Progress | 8/5/2022 | CRAIG VAUGHAN |
| Permit Finaled | 8/11/2022 | DEROLD HAUFF |
| CofO Issued | 8/11/2022 | DEROLD HAUFF |
| Permit Finaled | 8/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/14/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 1/14/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 1/14/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 1/14/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 1/14/2021 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 1/21/2021 | PATRICK MISCHLICH |
| Distance to fire station | Cleared | 4/29/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 5/6/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 5/19/2021 | RENZ SORIANO |
Contact Information
| Architect | Sundius,, Bo Kyle; Lic. No.: C38566 | , |
| Contractor | Lightning Construction & Design Inc; Lic. No.: 951122-B | 6047 TAMPA AVE #303 TARZANA, CA 91356 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/2/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/17/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/13/2021 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 10/13/2021 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 11/1/2021 | Partial Inspection | COREY HUPP |
| Wood Frame | 11/15/2021 | Partial Approval | MASHEL JONGERT |
| Wood Frame | 11/19/2021 | Partial Approval | COREY HUPP |
| Deputy Wood Construction | 12/21/2021 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/30/2021 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Rough | 12/30/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/30/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 12/30/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 1/4/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 1/4/2022 | Approved | CRAIG VAUGHAN |
| Wood Frame | 1/4/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 1/31/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 1/31/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/3/2022 | Approved | OSVALDO PARAMO |
| Green Building Rough | 2/3/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 2/3/2022 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 2/3/2022 | Approved | OSVALDO PARAMO |
| Insulation | 2/7/2022 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 2/11/2022 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/11/2022 | Partial Approval | SCOTT FINNILA |
| Gas Test | 6/8/2022 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 6/17/2022 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 6/17/2022 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 6/17/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 6/17/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 6/24/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 6/24/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 6/24/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 6/24/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 6/24/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 6/24/2022 | Approved | CRAIG VAUGHAN |
| Final | 7/1/2022 | Partial Inspection | AMY COLIN |
| ELECTRICAL-Final | 8/4/2022 | Approved | CRAIG VAUGHAN |
| Final | 8/4/2022 | OK to Issue CofO | CRAIG VAUGHAN |