3659 N ARMOUR AVE 90032

Certificate Information: 3659 N ARMOUR AVE 90032

Application / Permit
20014-10000-04779
Plan Check / Job No.
B20LA20123
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 11/29/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/25/2020 DANIEL YIP
Corrections Issued 11/30/2020 DANIEL YIP
Quality Review Completed 12/9/2020 ALLEN MANALANSAN
Building Plans Picked Up 12/29/2020 APPLICANT
Applicant returned to address corrections 10/25/2023 DANIEL YIP
Applicant returned to address corrections 11/20/2023 DANIEL YIP
Plan Check Approved 11/22/2023 DANIEL YIP
Issued 11/29/2023 APPLICANT
CofO in Progress 5/29/2025 LILIANA PORTILLO
Permit Finaled 5/31/2025 DEROLD HAUFF
CofO Issued 5/31/2025 DEROLD HAUFF
Permit Finaled 5/31/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/7/2021 ELAINE LEI
BHO/Hillside ordinance Cleared 4/7/2021 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 4/7/2021 ELAINE LEI
Hydrant and Access approval Cleared 4/26/2021 MATTHEW CRAIG
"D" conditions Cleared 3/9/2023 ANACANY HURTADO
"Q" conditions Cleared 3/9/2023 ANACANY HURTADO
ZI Cleared 3/9/2023 ANACANY HURTADO
Grading Pre-Inspection Cleared 3/17/2023 KIRK LINKLATER
GPI Written Notices Cleared 11/22/2023 DANIEL YIP

Contact Information

Contractor G A Design Build; Lic. No.: 941130-B 8449 EVEREST ST      DOWNEY, CA 90242
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/1/2023 Approved AMY COLIN
Wood Frame 12/28/2023 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 3/11/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Corrections Issued LILIANA PORTILLO
HVAC-Rough 3/11/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 3/11/2024 Approved LILIANA PORTILLO
ELECTRICAL-Rough 3/21/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/21/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 3/26/2024 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 3/26/2024 Not Ready for Inspection LILIANA PORTILLO
Insulation 3/26/2024 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 4/2/2024 Approved BRENDAN MORELLI
Green Building Rough 4/2/2024 Approved BRENDAN MORELLI
Wood Frame 4/2/2024 Approved BRENDAN MORELLI
Insulation 4/9/2024 Approved LILIANA PORTILLO
Drywall Nailing 4/18/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/5/2024 Not Ready for Inspection LILIANA PORTILLO
Final 7/5/2024 Corrections Issued LILIANA PORTILLO
Gas Test 7/5/2024 Approved LILIANA PORTILLO
PLUMBING-Final 7/5/2024 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 7/5/2024 Not Ready for Inspection LILIANA PORTILLO
Final 5/22/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 5/22/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/22/2025 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 5/22/2025 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 5/28/2025 Approved LILIANA PORTILLO
Final 5/28/2025 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 5/28/2025 Approved LILIANA PORTILLO
PLUMBING-Final 5/28/2025 Approved LILIANA PORTILLO
Smoke Detectors 5/28/2025 Approved LILIANA PORTILLO