1187 S HAUSER BLVD 90019
Certificate Information: 1187 S HAUSER BLVD 90019
- Application / Permit
- 20014-10000-04768
- Plan Check / Job No.
- B20LA20090
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ADDITION TO (E) GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c)
- Permit Issued
- Issued on 2/16/2021
- Issuing Office
- Current Status
- CofO Issued on 1/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2020 | DANIEL YIP |
| Corrections Issued | 11/12/2020 | DANIEL YIP |
| Building Plans Picked Up | 11/19/2020 | APPLICANT |
| Applicant returned to address corrections | 1/7/2021 | FERNANDO FLORES |
| Plan Check Approved | 1/12/2021 | FERNANDO FLORES |
| Issued | 2/16/2021 | APPLICANT |
| CofO in Progress | 9/28/2021 | ARTHUR SARGSYAN |
| CofO in Progress | 9/28/2021 | ARTHUR SARGSYAN |
| Permit Finaled | 1/28/2022 | DEROLD HAUFF |
| CofO Issued | 1/28/2022 | DEROLD HAUFF |
| Permit Finaled | 1/28/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/11/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2020 | THOMAS LANG |
| Sewer availability | Cleared | 12/31/2020 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chen,, Yeshen Jason; Lic. No.: C40169 | 20601 ALDA CT WALNUT, CA 91789 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/22/2021 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/3/2021 | Corrections Issued | DAVID FEILER |
| METHANE-Barrier | 3/3/2021 | Not Ready for Inspection | DAVID FEILER |
| METHANE-Subgrade | 3/3/2021 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 3/8/2021 | Partial Approval | RUBEN SALAS |
| METHANE-Barrier | 3/8/2021 | Approved | RUBEN SALAS |
| METHANE-Subgrade | 3/8/2021 | Approved | RUBEN SALAS |
| Footing/Foundation/Slab | 3/18/2021 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 3/26/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/6/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 5/6/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Rough | 5/6/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 5/6/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/6/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/18/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 5/18/2021 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/26/2021 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 6/2/2021 | Partial Approval | SCOTT FINNILA |
| Insulation | 6/7/2021 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/15/2021 | Approved | STUART CHAPMAN |
| Drywall Nailing | 6/24/2021 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 6/24/2021 | Approved | CALEB MEISTER |
| Sewer | 7/1/2021 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 7/1/2021 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 7/2/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 8/11/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Gas Test | 8/11/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 8/11/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 9/10/2021 | Corrections Issued | STUART CHAPMAN |
| Final | 9/10/2021 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Final | 9/10/2021 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Final | 9/10/2021 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 9/10/2021 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 9/10/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 9/10/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 9/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 9/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 9/27/2021 | OK to Issue CofO | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/27/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Service/Power Release | 9/27/2021 | Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 9/27/2021 | Approved | ARTHUR SARGSYAN |