5257 E RAPHAEL ST 90042

Certificate Information: 5257 E RAPHAEL ST 90042

Application / Permit
20014-10000-04736
Plan Check / Job No.
B20LA20009
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 40'0" X 11'9" TO FRONT OF (E) DWELLING FOR NEW TANDEM 2 CAR GARAGE.
Permit Issued
Issued on 4/27/2021
Issuing Office
Current Status
CofO Issued on 10/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/3/2020 APPLICANT
Assigned to Plan Check Engineer 11/18/2020 STANLEY RAAP
Corrections Issued 11/18/2020 STANLEY RAAP
Applicant returned to address corrections 2/4/2021 FARSHAD ALIMOHAMADI
Building Plans Picked Up 2/10/2021 APPLICANT
Applicant returned to address corrections 3/4/2021 FERNANDO FLORES
Plan Check Approved 3/8/2021 FERNANDO FLORES
Issued 4/27/2021 APPLICANT
CofO in Progress 9/30/2021 HAMIK HARTOUNIAN
CofO Issued 10/2/2021 DEROLD HAUFF
Permit Finaled 10/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/10/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 12/11/2020 CECILIO NAVARRO
CPC Cleared 12/14/2020 KATIE DEBIASE
HPOZ Cleared 12/14/2020 KATIE DEBIASE
Miscellaneous Cleared 12/14/2020 KATIE DEBIASE
Miscellaneous Cleared 12/14/2020 KATIE DEBIASE
Grading Pre-Inspection Cleared 12/30/2020 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng David; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/20/2021 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 5/26/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/3/2021 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/23/2021 Partial Approval SCOTT FINNILA
Green Building Rough 7/23/2021 Approved SCOTT FINNILA
BUILDING-Rough-Frame 7/26/2021 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/28/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 9/3/2021 Approved HORACE FULTZ
Final 9/3/2021 Conditional Approval HORACE FULTZ
Footing/Foundation/Slab 9/3/2021 Approved HORACE FULTZ
Green Building Final 9/3/2021 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 9/3/2021 SGSOV Approved HORACE FULTZ
Smoke Detectors 9/3/2021 Approved HORACE FULTZ
Final 9/21/2021 Corrections Issued HAMIK HARTOUNIAN
Final 9/29/2021 OK to Issue CofO HAMIK HARTOUNIAN