536 N MARIE AVE 90042
Certificate Information: 536 N MARIE AVE 90042
- Application / Permit
- 20014-10000-04682
- Plan Check / Job No.
- B20LA19753
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) ATTACHED PATIO. NEW 12'-10" x 25'-2" ADDITION AT REAR OF EXISTING SINGLE FAMILY DWELLING. REFRAME ENTRY BETWEEN THE EXISTING HOUSE AND ADDITION. NEW FRENCH DOORS, WINDOWS, SKYLIGHTS, CEILING FANS.
- Permit Issued
- Issued on 9/17/2021
- Issuing Office
- Current Status
- CofO Issued on 12/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2020 | ZAW HAN |
| Corrections Issued | 11/9/2020 | ZAW HAN |
| Applicant returned to address corrections | 12/30/2020 | GEORGE ALVAREZ |
| Building Plans Picked Up | 1/6/2021 | APPLICANT |
| Plan Check Approved | 6/28/2021 | RAHEL BEYENE |
| Issued | 9/17/2021 | APPLICANT |
| CofO in Progress | 12/5/2023 | AMY COLIN |
| Permit Finaled | 12/7/2023 | DEROLD HAUFF |
| CofO Issued | 12/7/2023 | DEROLD HAUFF |
| Permit Finaled | 12/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/4/2021 | ZAW HAN |
| Miscellaneous | Cleared | 2/10/2021 | RICHARD REASER |
| ZA Case | Cleared | 2/10/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 2/11/2021 | MARC WOERSCHING |
| Miscellaneous | Cleared | 2/11/2021 | MARC WOERSCHING |
| Miscellaneous | Cleared | 2/16/2021 | MARC WOERSCHING |
| BHO/Hillside ordinance | Cleared | 2/22/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 2/22/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 2/22/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 2/23/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 2/23/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 2/23/2021 | WALLIE JONG |
| Sewer availability | Cleared | 2/23/2021 | WALLIE JONG |
| Certificate of Compliance | Cleared | 5/21/2021 | MARC WOERSCHING |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2021 | WALLIE JONG |
Contact Information
| Architect | Uriu,, Scott Darrell; Lic. No.: C29372 | 441 PUNAHOU STREET ALTADENA, CA 91001 |
| Contractor | Treeium Inc; Lic. No.: 617148-B | 5352 LAUREL CANYON BLVD #200 VALLEY VILLAGE, CA 91607 |
| Engineer | Canterberry,, Larry Glen; Lic. No.: L8776 | 5210 MOLISE COURT BAKERSFIELD, CA 93308 |
| Engineer | Zangoli,, Fabio; Lic. No.: S6191 | 13245 FIJI WY UNIT J MARINA DEL REY, CA 90292 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/1/2021 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 11/5/2021 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 11/19/2021 | Not Ready for Inspection | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 11/23/2021 | Approved | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 12/13/2021 | Approved | COREY HUPP |
| Deputy Drilled-In Anchors | 12/15/2021 | Conditional Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 1/6/2022 | Not Ready for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 1/28/2022 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2022 | Corrections Issued | AMY COLIN |
| Deputy Wood Construction | 2/1/2022 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/2/2022 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 2/2/2022 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 2/2/2022 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 2/2/2022 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 2/2/2022 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 2/8/2022 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 2/8/2022 | Approved | COREY HUPP |
| Final | 3/2/2022 | Partial Inspection | COREY HUPP |
| Footing/Foundation/Slab | 3/2/2022 | Approved | COREY HUPP |
| Green Building Final | 3/2/2022 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 3/2/2022 | SGSOV Approved | COREY HUPP |
| Smoke Detectors | 3/2/2022 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Final | 3/8/2022 | Approved | SCOTT FINNILA |
| Final | 3/8/2022 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 3/8/2022 | Approved | SCOTT FINNILA |
| HVAC-Final | 3/8/2022 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 3/8/2022 | Corrections Issued | SCOTT FINNILA |
| Smoke Detectors | 3/8/2022 | Approved | SCOTT FINNILA |
| Pre-Inspection | 10/17/2022 | Partial Inspection | AMY COLIN |
| Deputy Drilled-In Anchors | 10/3/2023 | Approved | ROY SPAULDING |
| Final | 10/10/2023 | Corrections Issued | ROY SPAULDING |
| Final | 12/4/2023 | OK to Issue CofO | AMY COLIN |