5215 N MOUNT HELENA AVE 90041

Certificate Information: 5215 N MOUNT HELENA AVE 90041

Application / Permit
20014-10000-04680
Plan Check / Job No.
B20LA19736
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SFD FOR NEW BATH AND NEW UNCOVERED DECK.
Permit Issued
Issued on 1/8/2021
Issuing Office
Current Status
CofO Issued on 4/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2020 APPLICANT
Assigned to Plan Check Engineer 11/2/2020 ZAW HAN
Corrections Issued 11/9/2020 ZAW HAN
Plan Check Approved 1/5/2021 FARSHAD ALIMOHAMADI
Issued 1/8/2021 APPLICANT
Building Plans Picked Up 1/12/2021 APPLICANT
CofO in Progress 4/19/2022 CRAIG VAUGHAN
CofO Issued 4/25/2022 DEROLD HAUFF
Permit Finaled 4/25/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/23/2020 KIRK LINKLATER
Roof/Waste drainage to street Cleared 12/10/2020 CELINA MORENO
Sewer availability Cleared 12/10/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/11/2020 CELINA MORENO

Contact Information

Contractor Requiem Builders & Design; Lic. No.: 1055466-B 2406 ELMGROVE STREET      LOS ANGELES, CA 90031
Engineer Jung,, Jason Stanley; Lic. No.: C80569 106 N ROSEMEAD BLVD STE 204      PASADENA, CA 91107

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2021 Corrections Issued COREY HUPP
Excavation/Setback/Form/Re-Bar 3/5/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/18/2021 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/18/2021 Approved BRIAN SULLIVAN
Green Building Rough 3/18/2021 Not Ready for Inspection BRIAN SULLIVAN
Piling/Pier/Caisson 3/19/2021 No Access for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 4/12/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 4/12/2021 Approved BRIAN SULLIVAN
Green Building Rough 4/12/2021 Approved BRIAN SULLIVAN
HVAC-Rough 4/12/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 4/12/2021 Corrections Issued BRIAN SULLIVAN
Insulation 4/23/2021 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 4/23/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 4/23/2021 Corrections Issued CRAIG VAUGHAN
Shower Pan 4/23/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/4/2021 Approved CRAIG VAUGHAN
Insulation 5/4/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/4/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/5/2021 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 5/5/2021 Approved CRAIG VAUGHAN
Insulation 5/5/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 5/5/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 5/5/2021 Approved CRAIG VAUGHAN
Shower Pan 5/5/2021 Approved CRAIG VAUGHAN
Drywall Nailing 5/18/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 5/18/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 4/18/2022 Approved CRAIG VAUGHAN
Final 4/18/2022 OK to Issue CofO CRAIG VAUGHAN
Footing/Foundation/Slab 4/18/2022 Approved CRAIG VAUGHAN
Green Building Final 4/18/2022 Approved CRAIG VAUGHAN
HVAC-Final 4/18/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 4/18/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/18/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 4/18/2022 Approved CRAIG VAUGHAN