1490 S DURANGO AVE 90035
Certificate Information: 1490 S DURANGO AVE 90035
- Application / Permit
- 20014-10000-04677
- Plan Check / Job No.
- B20LA19722
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Ground floor addition and second story addition to the (E) detached garage and conversion of entire building into a ADU.
- Permit Issued
- Issued on 3/23/2021
- Issuing Office
- Metro
- Current Status
- Issued on 3/23/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | HELEN NGUYEN |
| Corrections Issued | 11/9/2020 | HELEN NGUYEN |
| Building Plans Picked Up | 12/2/2020 | APPLICANT |
| Quality Review Completed | 12/23/2020 | MINYE PAK |
| Applicant returned to address corrections | 2/26/2021 | HELEN NGUYEN |
| Plan Check Approved | 3/11/2021 | HELEN NGUYEN |
| Issued | 3/23/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2020 | JEANIE LAM |
| Sewer availability | Cleared | 12/18/2020 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 1/20/2021 | KIRK LINKLATER |
| Hydrant and Access approval | Cleared | 1/20/2021 | MATTHEW CRAIG |
| Address approval | Cleared | 3/2/2021 | THOMAS LANG |
| GPI Written Notices | Cleared | 3/11/2021 | HELEN NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 12/6/2021 | Approved | EVAN COOPER |
| Underground Mechanical | 12/6/2021 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Corrections Issued | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 1/25/2022 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 2/4/2022 | Corrections Issued | EVAN COOPER |
| METHANE-Barrier | 2/4/2022 | Approved | EVAN COOPER |
| METHANE-Subgrade | 2/4/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 3/30/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 3/30/2022 | No Access for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 3/30/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 4/1/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 4/1/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 5/6/2022 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 6/10/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 6/10/2022 | Approved | EVAN COOPER |
| Green Building Rough | 6/10/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 6/10/2022 | Approved | EVAN COOPER |
| Insulation | 6/15/2022 | Not Ready for Inspection | EVAN COOPER |
| Insulation | 6/17/2022 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 7/14/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 11/16/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Final | 11/16/2022 | Approved | CLAYTON GRAHAM |
| Service/Power Release | 11/16/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 11/18/2022 | Approved | ASHLEY THOMPSON |
| Final | 11/18/2022 | Corrections Issued | ASHLEY THOMPSON |
| Gas Test | 11/18/2022 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 11/18/2022 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 11/18/2022 | Approved | ASHLEY THOMPSON |
| Service/Power Release | 11/18/2022 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 1/18/2023 | Not Ready for Inspection | JEREMY TODD |
| Final | 1/18/2023 | Not Ready for Inspection | JEREMY TODD |
| Footing/Foundation/Slab | 1/18/2023 | Not Ready for Inspection | JEREMY TODD |
| Green Building Final | 1/18/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 1/18/2023 | SGSOV Approved | JEREMY TODD |
| Smoke Detectors | 1/18/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 3/16/2023 | Not Ready for Inspection | JEREMY TODD |
| Final | 3/16/2023 | Not Ready for Inspection | JEREMY TODD |
| Footing/Foundation/Slab | 3/16/2023 | Not Ready for Inspection | JEREMY TODD |