3760 S SOMERSET DR 90016
Certificate Information: 3760 S SOMERSET DR 90016
- Application / Permit
- 20014-10000-04636
- Plan Check / Job No.
- B20LA19597
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION TO (E) SINGLE FAMILY DWELLING. INTERIOR REMODEL.
- Permit Issued
- Issued on 4/29/2021
- Issuing Office
- Current Status
- CofO Issued on 2/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | KEVIN MORALES |
| Corrections Issued | 12/4/2020 | KEVIN MORALES |
| Applicant returned to address corrections | 12/30/2020 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 2/9/2021 | ADAM HEGAZI |
| Plan Check Approved | 4/15/2021 | ADAM HEGAZI |
| Issued | 4/29/2021 | APPLICANT |
| Building Plans Picked Up | 5/3/2021 | APPLICANT |
| Refund in Progress | 2/15/2022 | SELENIA GARCIA |
| Refund Closed | 2/15/2022 | SELENIA GARCIA |
| Issued | 2/15/2022 | SELENIA GARCIA |
| CofO in Progress | 2/17/2022 | ANTHONY EGSON |
| CofO Issued | 2/17/2022 | DEROLD HAUFF |
| Permit Finaled | 2/17/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2021 | ROSA SILVA |
| Roof/Waste drainage to street | Cleared | 3/16/2021 | ROSA SILVA |
Contact Information
| Contractor | Cal Construction; Lic. No.: 921192-B | P O BOX 287 COMPTON, CA 90223 |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2622 DORSET DR TORRANCE, CA 90503 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/10/2021 | Partial Inspection | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 5/11/2021 | No Access for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 5/14/2021 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 5/14/2021 | Approved | DAVID FEILER |
| Insulation | 6/7/2021 | Not Ready for Inspection | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 6/7/2021 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 6/9/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/9/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 6/9/2021 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 6/9/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 6/9/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 7/20/2021 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 8/24/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 9/1/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 9/1/2021 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 9/7/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 9/7/2021 | Not Ready for Inspection | DAVID FEILER |
| Insulation | 9/7/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 9/16/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 9/16/2021 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 9/16/2021 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 9/27/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 9/27/2021 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 10/1/2021 | Corrections Issued | CALEB MEISTER |
| Interior/Exterior Lathing | 10/1/2021 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 10/1/2021 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Rough | 10/5/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 10/5/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 10/5/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 10/6/2021 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 10/6/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/6/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/15/2021 | Not Ready for Inspection | ADAM ESCOTO |
| ELECTRICAL-Rough | 10/15/2021 | Approved | ADAM ESCOTO |
| Green Building Rough | 10/15/2021 | Approved | ADAM ESCOTO |
| HVAC-Rough | 10/15/2021 | Approved | ADAM ESCOTO |
| Insulation | 10/15/2021 | Conditional Approval | ADAM ESCOTO |
| PLUMBING-Rough | 10/15/2021 | Approved | ADAM ESCOTO |
| Drywall Nailing | 10/19/2021 | Approved | LILIANA PORTILLO |
| Green Building Rough | 10/19/2021 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 10/19/2021 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/21/2021 | Partial Approval | HORACE FULTZ |
| Shower Pan | 10/21/2021 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 12/17/2021 | Approved | ANTHONY EGSON |
| Final | 12/17/2021 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 12/17/2021 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/17/2021 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 12/17/2021 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 12/22/2021 | Corrections Issued | HORACE FULTZ |
| HVAC-Final | 12/22/2021 | Corrections Issued | HORACE FULTZ |
| PLUMBING-Final | 12/22/2021 | Corrections Issued | HORACE FULTZ |
| Final | 12/27/2021 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 12/27/2021 | Corrections Issued | ANTHONY EGSON |
| Smoke Detectors | 12/27/2021 | Partial Inspection | ANTHONY EGSON |
| Final | 1/3/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 1/3/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 1/3/2022 | Corrections Issued | ANTHONY EGSON |
| Smoke Detectors | 1/3/2022 | Approved | ANTHONY EGSON |
| Final | 1/31/2022 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 1/31/2022 | Approved | ANTHONY EGSON |