123 N GRAMERCY PL 90004

Certificate Information: 123 N GRAMERCY PL 90004

Application / Permit
20014-10000-04634
Plan Check / Job No.
B20LA19593
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING SFD
Permit Issued
Issued on 1/30/2021
Issuing Office
Current Status
CofO Issued on 11/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/26/2020 APPLICANT
Assigned to Plan Check Engineer 11/2/2020 STARR CHEN
Corrections Issued 11/4/2020 STARR CHEN
Plan Check Approved 12/7/2020 CARLOS MONTES
Issued 1/30/2021 APPLICANT
Building Plans Picked Up 2/4/2021 APPLICANT
CofO in Progress 11/3/2021 MASHEL JONGERT
Permit Finaled 11/29/2021 DEROLD HAUFF
CofO Issued 11/29/2021 DEROLD HAUFF
Permit Finaled 11/29/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/18/2020 CECILIO NAVARRO
Sewer availability Cleared 11/18/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 11/19/2020 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/16/2021 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/16/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/29/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 4/29/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/20/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/20/2021 Partial Approval CHRIS CHRISTENSEN
Gas Test 5/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 5/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 5/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/16/2021 Approved CHRIS CHRISTENSEN
Gas Test 6/16/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 6/16/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/16/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 6/16/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 6/22/2021 Corrections Issued ALFREDO BALANDRA
Insulation 6/22/2021 Corrections Issued ALFREDO BALANDRA
Green Building Rough 6/24/2021 Approved CHARLES BOGHOSKHAN
Insulation 6/24/2021 Approved CHARLES BOGHOSKHAN
Drywall Nailing 6/29/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 7/20/2021 Approved JOSEPH MCGARRY
Shower Pan 7/20/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Final 10/25/2021 Approved CHRIS CHRISTENSEN
Final 10/25/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 10/25/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 10/25/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/25/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/25/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 10/25/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 10/27/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 10/27/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/27/2021 Approved CHRIS CHRISTENSEN
Final 11/3/2021 OK to Issue CofO MASHEL JONGERT
Green Building Final 11/3/2021 Approved MASHEL JONGERT