2352 W RIPPLE ST 90039
Certificate Information: 2352 W RIPPLE ST 90039
- Application / Permit
- 20014-10000-04628
- Plan Check / Job No.
- B20LA19570
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- CHANGE OF USE FROM LIGHT MANUFACTURING AND GARAGE TO OFFICE. NEW 2ND FLOOR ADDITION. NEW ACCESSIBLE RESTROOMS. DOOR AND WINDOW REPLACEMENT AND ALTERATION. RELOCATE EXISTING PARKING OFFSITE. (1 OF 2)
- Permit Issued
- Issued on 3/11/2021
- Issuing Office
- Current Status
- CofO Issued on 7/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2020 | KEVIN MORALES |
| Corrections Issued | 12/4/2020 | KEVIN MORALES |
| Quality Review Completed | 12/8/2020 | EUGENE BARBEAU |
| Disabled Access Plans Picked Up | 12/16/2020 | APPLICANT |
| Applicant returned to address corrections | 12/21/2020 | KEVIN MORALES |
| Green Plans Picked Up | 1/7/2021 | APPLICANT |
| Plan Check Approved | 3/10/2021 | KEVIN MORALES |
| Issued | 3/11/2021 | APPLICANT |
| Building Plans Picked Up | 3/16/2021 | APPLICANT |
| CofO in Progress | 7/29/2024 | RONALD JIMENEZ |
| Permit Finaled | 7/30/2024 | RAFAEL ESPINOZA |
| CofO Issued | 7/30/2024 | RAFAEL ESPINOZA |
| Permit Finaled | 7/30/2024 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/22/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 1/6/2021 | CECILIO NAVARRO |
| Work Adjacent to Public Way | Cleared | 1/8/2021 | ARMEN SARKISIAN |
| Encroachment in public way | Cleared | 1/11/2021 | ELENA LOPEZ |
| ZI | Cleared | 1/19/2021 | RICHARD REASER |
| DAS Clearance | Cleared | 2/18/2021 | KEVIN MORALES |
| Green Code | Cleared | 3/5/2021 | KEVIN MORALES |
Contact Information
| Contractor | Arroyo Hill Development Inc; Lic. No.: 889164-B | 3579 E FOOTHILL BLVD 311 LOS ANGELES, CA 91107 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 4/19/2021 | Conditional Approval | LANNY MERRICK |
| Deputy Other (see comments) | 4/22/2021 | Conditional Approval | RONALD PACHECO |
| Deputy Drilled-In Anchors | 4/29/2021 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 4/29/2021 | Conditional Approval | LANNY MERRICK |
| Footing/Foundation/Slab | 4/29/2021 | Approved | LANNY MERRICK |
| Deputy Drilled-In Anchors | 4/30/2021 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 4/30/2021 | Conditional Approval | LANNY MERRICK |
| Deputy Steel/Welding | 6/3/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 6/4/2021 | Conditional Approval | LANNY MERRICK |
| Deputy Steel/Welding | 6/7/2021 | Conditional Approval | LANNY MERRICK |
| Deputy Steel/Welding | 6/8/2021 | Conditional Approval | LANNY MERRICK |
| Deputy Steel/Welding | 6/9/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 6/14/2021 | Conditional Approval | JONATHAN QUACH |
| Green Building Rough | 6/17/2021 | Approved | LANNY MERRICK |
| Reinforced Concrete Frame | 6/17/2021 | Approved | LANNY MERRICK |
| Deputy Drilled-In Anchors | 6/25/2021 | Conditional Approval | LANNY MERRICK |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2021 | Partial Approval | LANNY MERRICK |
| Wood Frame | 7/1/2021 | Partial Approval | LANNY MERRICK |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2021 | Partial Approval | LANNY MERRICK |
| Deputy Steel/Welding | 7/12/2021 | Conditional Approval | LANNY MERRICK |
| Wood Frame | 7/19/2021 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 7/21/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 7/28/2021 | Approved | LANNY MERRICK |
| Final | 11/23/2021 | Not Ready for Inspection | MARK FERRARI |
| Green Building Final | 11/23/2021 | Not Ready for Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 11/23/2021 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 11/23/2021 | Approved | MARK FERRARI |
| Structural Steel Frame | 11/23/2021 | Conditional Approval | MARK FERRARI |
| Wood Frame | 11/23/2021 | Approved | MARK FERRARI |
| Final | 11/30/2021 | Not Ready for Inspection | MARK FERRARI |
| Green Building Final | 11/30/2021 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 11/30/2021 | SGSOV Approved | MARK FERRARI |
| Structural Steel Frame | 11/30/2021 | Approved | MARK FERRARI |
| Final | 12/7/2021 | Conditional Approval | MARK FERRARI |
| Final | 12/15/2021 | Conditional Approval | MARK FERRARI |
| Final | 9/12/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 6/17/2024 | Conditional Approval | RONALD JIMENEZ |
| Final | 7/29/2024 | OK to Issue CofO | RONALD JIMENEZ |