10411 S KALMIA ST 90002
Certificate Information: 10411 S KALMIA ST 90002
- Application / Permit
- 20014-10000-04627
- Plan Check / Job No.
- B20LA19564
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO REAR OF SFD (240.5 SF)
- Permit Issued
- Issued on 4/5/2021
- Issuing Office
- Current Status
- CofO Issued on 1/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2020 | LUKE GONZALES |
| Corrections Issued | 11/2/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 12/10/2020 | FERNANDO FLORES |
| Plan Check Approved | 3/4/2021 | LUKE GONZALES |
| Issued | 4/5/2021 | APPLICANT |
| Building Plans Picked Up | 4/8/2021 | APPLICANT |
| CofO in Progress | 12/28/2021 | EUGENE CASSIDY |
| Permit Finaled | 1/5/2022 | RONALD MYRICK |
| CofO Issued | 1/5/2022 | RONALD MYRICK |
| Permit Finaled | 1/5/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/24/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2020 | THOMAS LANG |
| Address approval | Cleared | 1/5/2021 | WALLIE JONG |
Contact Information
| Contractor | Zetino And Son'S Construction; Lic. No.: 817787-B | 841 S CALIFORNIA AVE WEST COVINA, CA 91790 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/20/2021 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 4/26/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/13/2021 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2021 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 5/20/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2021 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 5/27/2021 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 6/1/2021 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/2/2021 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/2/2021 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 8/2/2021 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 8/2/2021 | Corrections Issued | EUGENE CASSIDY |
| Special/Order Compliance | 8/2/2021 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 8/2/2021 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/10/2021 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/10/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 8/10/2021 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 8/10/2021 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/7/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/7/2021 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 9/7/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/7/2021 | Approved | EUGENE CASSIDY |
| Insulation | 9/21/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/21/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 9/27/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/30/2021 | No Access for Inspection | EUGENE CASSIDY |
| Final | 11/30/2021 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 11/30/2021 | No Access for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 11/30/2021 | No Access for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/30/2021 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 11/30/2021 | No Access for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 11/30/2021 | No Access for Inspection | EUGENE CASSIDY |
| Final | 12/3/2021 | Corrections Issued | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 12/3/2021 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 12/3/2021 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 12/9/2021 | Approved | EUGENE CASSIDY |
| Final | 12/9/2021 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 12/9/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 12/9/2021 | Approved | EUGENE CASSIDY |
| Service/Power Release | 12/9/2021 | No Access for Inspection | EUGENE CASSIDY |
| Final | 12/21/2021 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/27/2021 | Approved | EUGENE CASSIDY |
| Final | 12/27/2021 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 12/27/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 12/27/2021 | Approved | EUGENE CASSIDY |
| Service/Power Release | 12/27/2021 | Not Required | EUGENE CASSIDY |