8356 S NAYLOR AVE 90045
Certificate Information: 8356 S NAYLOR AVE 90045
- Application / Permit
- 20014-10000-04626
- Plan Check / Job No.
- B20LA19563
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- Current Status
- Issued on 4/12/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | KEVIN MORALES |
| Corrections Issued | 12/4/2020 | KEVIN MORALES |
| Applicant returned to address corrections | 12/30/2020 | SAMUEL GONZALEZ |
| Plan Check Approved | 4/9/2021 | KEVIN MORALES |
| Issued | 4/12/2021 | APPLICANT |
| Building Plans Picked Up | 4/14/2021 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/18/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | DENNIS BRAGIN |
Contact Information
| Contractor | Cal Construction; Lic. No.: 921192-B | P O BOX 287 COMPTON, CA 90223 |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2622 DORSET DR TORRANCE, CA 90503 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/27/2021 | Corrections Issued | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 4/29/2021 | Conditional Approval | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 4/30/2021 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 5/18/2021 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 5/18/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 5/18/2021 | Approved | BRENDAN LOONEY |
| Insulation | 5/19/2021 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 5/24/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 5/24/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 5/24/2021 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 5/27/2021 | Partial Approval | BRENDAN LOONEY |
| HVAC-Rough | 5/27/2021 | Partial Approval | BRENDAN LOONEY |
| Insulation | 5/28/2021 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2021 | Partial Approval | DONALD GALLAGHER |
| Drywall Nailing | 6/23/2021 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 6/23/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2021 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2021 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 7/19/2021 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Conditional Approval | BRENDAN LOONEY |
| HVAC-Rough | 7/19/2021 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 7/19/2021 | Approved | BRENDAN LOONEY |
| Shower Pan | 7/19/2021 | Approved | BRENDAN LOONEY |
| Insulation | 7/22/2021 | Approved | BRENDAN LOONEY |
| Deputy Wood Construction | 7/23/2021 | Conditional Approval | BRENDAN LOONEY |
| Drywall Nailing | 8/3/2021 | Approved | MORRIS JACKSON |
| Green Building Rough | 8/3/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 8/10/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 8/19/2021 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/20/2021 | Approved | ENRIQUE MIRELES |
| Final | 10/20/2021 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/20/2021 | Approved | ENRIQUE MIRELES |
| Green Building Final | 10/20/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 10/20/2021 | Approved | ENRIQUE MIRELES |
| Final | 10/25/2021 | Corrections Issued | DAVID FEILER |